CompTIA Project+ PK0-005 Study Guide - Chapter 10

CompTIA Project+ PK0-005 Study Guide - Chapter 10

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Patrick Pepin

Used 1+ times

FREE Resource

Student preview

quiz-placeholder

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action.

It turns out the glitch was an unintentional enhancement to the product, and the marketing people are enthused about its potential.

The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement.

As the project manager, you know that a variance has occurred.

Which of the following is not true?

Common causes of variance are situations that are unique and not easily controlled at the operational level.

  1. Random variances, known or predictable variances, and variances that are always present in the process are known as common causes of variance.

  1. Inspection determines whether measurements fall within tolerable results.

Scatter diagrams display the relationships between an independent and a dependent variable to show variations in the process over time.

Answer explanation

Common causes of variance are situations that are common to the process you're using and are easily controlled at the operational level

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have just left a meeting with the project sponsor where you were advised that your project has been canceled because of budget cuts.

You have called the project team together to fill them in and to review the remaining activities to close out the project.

Several of your team members question the benefit of doing a lessons learned review on a project that has been canceled.

What should your response be?

Advise the team that part of the review time will be spent on documenting the failure of the lack of clear requirements from the customer.

Tell the team they need to do this to be able to stay on the project payroll another week while they look for a new assignment.

  1. Inform the team that a final report is a requirement from the PMO, regardless of how the project ends.

Explain that there is value both to the team and for future projects in analyzing the phases of the project that have been completed to date to document what went right, what went wrong, and what you would change.

Answer explanation

There is valuable information to be gained from a review of any project, even projects that do not complete.

The assessment should focus on those phases of the project that did finish, as well as a look at whether anything could have been done differently to make the project a success.

The purpose of lessons learned is not to assign blame, even for projects that are canceled

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You have just left a meeting with the project sponsor where you were advised that your project has been canceled because of budget cuts.

You have called the project team together to fill them in and to review the remaining activities to close out the project.

Which of the following describes the type of project ending this project experienced?

Extinction

Starvation

Addition

Integration

Answer explanation

  1. Starvation is a project ending caused by resources being cut off from the project.


  2. Extinction occurs when the project work is completed and is accepted by the stakeholders.


  3. Addition occurs when projects evolve into ongoing operations, and integration occurs when resources are distributed to other areas of the organization.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following measurement tools are used to measure operational or performance goals for projects?

KPIs

  1. Key objectives

Balanced scorecard

Key results

All of the above

Answer explanation

KPIs are used to measure any element of the project or operational areas of the business to determine whether goals are being achieved.

A balanced scorecard is used to determine whether organizational goals are being met

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the "best" type of project ending?

Extinction

Addition

Integration

Starvation

Answer explanation

Extinction occurs when the project work is completed and is accepted by the stake-holders.

This is the best type of project ending.

Starvation is a project ending caused by resources being cut off from the project.

Addition occurs when projects evolve into ongoing operations, and integration occurs when resources are distributed to other areas of the organization

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a formal sign-off at the conclusion of the project work?

The sign-off allows the project manager to start a new assignment.

The sign-off means the project team is no longer accountable for the product of the project.

The sign-off is the trigger for releasing team members back to their functional organization.

The sign-off indicates that the project meets the documented requirements and the customer has accepted the project deliverables.

Answer explanation

A sign-off is the formal acceptance of the project's final product, service, or result.

Its primary purpose is the customer's acceptance of the product of the project.

Team members are released after sign-off, but this isn't the primary purpose of a formal sign-off.

Both the project manager and the project team members may continue to be involved in the project until all closure activities are complete

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following charts is a type of histogram?

Scatter diagram

Fishbone

Pareto chart

  1. Run chart

Answer explanation

A Pareto diagram is a type of histogram that measures the frequency of occurrences of data elements in rank order over time

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?