CompTIA Project+ PK0-005 Study Guide - Chapter 10

Quiz
•
Professional Development
•
Professional Development
•
Medium

Patrick Pepin
Used 1+ times
FREE Resource
Student preview

20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action.
It turns out the glitch was an unintentional enhancement to the product, and the marketing people are enthused about its potential.
The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement.
As the project manager, you know that a variance has occurred.
Which of the following is not true?
Common causes of variance are situations that are unique and not easily controlled at the operational level.
Random variances, known or predictable variances, and variances that are always present in the process are known as common causes of variance.
Inspection determines whether measurements fall within tolerable results.
Scatter diagrams display the relationships between an independent and a dependent variable to show variations in the process over time.
Answer explanation
Common causes of variance are situations that are common to the process you're using and are easily controlled at the operational level
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You have just left a meeting with the project sponsor where you were advised that your project has been canceled because of budget cuts.
You have called the project team together to fill them in and to review the remaining activities to close out the project.
Several of your team members question the benefit of doing a lessons learned review on a project that has been canceled.
What should your response be?
Advise the team that part of the review time will be spent on documenting the failure of the lack of clear requirements from the customer.
Tell the team they need to do this to be able to stay on the project payroll another week while they look for a new assignment.
Inform the team that a final report is a requirement from the PMO, regardless of how the project ends.
Explain that there is value both to the team and for future projects in analyzing the phases of the project that have been completed to date to document what went right, what went wrong, and what you would change.
Answer explanation
There is valuable information to be gained from a review of any project, even projects that do not complete.
The assessment should focus on those phases of the project that did finish, as well as a look at whether anything could have been done differently to make the project a success.
The purpose of lessons learned is not to assign blame, even for projects that are canceled
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You have just left a meeting with the project sponsor where you were advised that your project has been canceled because of budget cuts.
You have called the project team together to fill them in and to review the remaining activities to close out the project.
Which of the following describes the type of project ending this project experienced?
Extinction
Starvation
Addition
Integration
Answer explanation
Starvation is a project ending caused by resources being cut off from the project.
Extinction occurs when the project work is completed and is accepted by the stakeholders.
Addition occurs when projects evolve into ongoing operations, and integration occurs when resources are distributed to other areas of the organization.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following measurement tools are used to measure operational or performance goals for projects?
KPIs
Key objectives
Balanced scorecard
Key results
All of the above
Answer explanation
KPIs are used to measure any element of the project or operational areas of the business to determine whether goals are being achieved.
A balanced scorecard is used to determine whether organizational goals are being met
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the "best" type of project ending?
Extinction
Addition
Integration
Starvation
Answer explanation
Extinction occurs when the project work is completed and is accepted by the stake-holders.
This is the best type of project ending.
Starvation is a project ending caused by resources being cut off from the project.
Addition occurs when projects evolve into ongoing operations, and integration occurs when resources are distributed to other areas of the organization
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of a formal sign-off at the conclusion of the project work?
The sign-off allows the project manager to start a new assignment.
The sign-off means the project team is no longer accountable for the product of the project.
The sign-off is the trigger for releasing team members back to their functional organization.
The sign-off indicates that the project meets the documented requirements and the customer has accepted the project deliverables.
Answer explanation
A sign-off is the formal acceptance of the project's final product, service, or result.
Its primary purpose is the customer's acceptance of the product of the project.
Team members are released after sign-off, but this isn't the primary purpose of a formal sign-off.
Both the project manager and the project team members may continue to be involved in the project until all closure activities are complete
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following charts is a type of histogram?
Scatter diagram
Fishbone
Pareto chart
Run chart
Answer explanation
A Pareto diagram is a type of histogram that measures the frequency of occurrences of data elements in rank order over time
Create a free account and access millions of resources
Popular Resources on Wayground
12 questions
Unit Zero lesson 2 cafeteria

Lesson
•
9th - 12th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
20 questions
Lab Safety and Equipment

Quiz
•
8th Grade
13 questions
25-26 Behavior Expectations Matrix

Quiz
•
9th - 12th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade
Discover more resources for Professional Development
11 questions
All about me

Quiz
•
Professional Development
10 questions
How to Email your Teacher

Quiz
•
Professional Development
5 questions
Setting goals for the year

Quiz
•
Professional Development
7 questions
How to Email your Teacher

Quiz
•
Professional Development
20 questions
Employability Skills

Quiz
•
Professional Development