Which of the following is not a key component of scope planning?

Work breakdown structure (WBS)

Scope statement

Project charter

Scope management plan

Answer explanation

The key components of scope planning are the scope management plan, scope statement, and work breakdown structure.

The project charter is created during initiation

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The scope statement provides which of the following?

A basis for a common understanding of the project and for making future decisions regarding the project

A detailed list of all resources required for project completion

  1. A schedule of all the key project activities

A process for managing change control

Answer explanation

The scope statement serves as a basis for understanding the work of the project and for future decision-making

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following are components of a scope statement? (Choose three.)

General project approach

Project description

Assumptions and constraints

Stakeholder list

Exclusions

Answer explanation

The sections of a scope statement are project description, key deliverables, success and acceptance criteria, exclusions, time and cost estimates, assumptions, and constraints

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following describes influencers? (select all that apply)

Influencers can impact, change, or create a new constraint.

Scope creep is an example of an influencer.

Change request is an influencer.

Interaction between constraints is an example of an influencer.

Answer explanation

All of the options describe and provide examples of influences

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following involves changing the project or product scope without considering the impacts it will have to the project schedule, budget, and scope statement?

  1. Change request

Scope creep

Stakeholder/management directive

Quality deficiency

Answer explanation

Scope creep involves changing the product or project scope without regard to impacts to the schedule, budget, and/or resources.

KPIs are key performance indicators that help you incrementally monitor project performance

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

There are three primary constraints on most projects.

Your customer, or project sponsor, will stipulate which of the three is the most important to them.

Which three are the typical constraints found on the majority of projects? (Choose three.)

Budget

Team members

Scope

Quality

Time

Answer explanation

They are budget, scope, and time, all of which impact quality

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your sprint is nearing completion.

The product owner reminds you they will not accept the deliverable unless it measures 3 centimeters exactly. If the measurements are off, the next sprint will be delayed, and the entire project could be at risk.

This is an example of which of the following?

Acceptance criteria

Change request

  1. Stability of scope

  1. Product scope description

Answer explanation

This is an example of acceptance criteria for the user story

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?