Which of the following is not a key component of scope planning?
CompTIA Project+ PK0-005 Study Guide - Chapter 04

Quiz
•
Professional Development
•
Professional Development
•
Medium

Patrick Pepin
Used 1+ times
FREE Resource
Student preview

20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Work breakdown structure (WBS)
Scope statement
Project charter
Scope management plan
Answer explanation
The key components of scope planning are the scope management plan, scope statement, and work breakdown structure.
The project charter is created during initiation
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The scope statement provides which of the following?
A basis for a common understanding of the project and for making future decisions regarding the project
A detailed list of all resources required for project completion
A schedule of all the key project activities
A process for managing change control
Answer explanation
The scope statement serves as a basis for understanding the work of the project and for future decision-making
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which of the following are components of a scope statement? (Choose three.)
General project approach
Project description
Assumptions and constraints
Stakeholder list
Exclusions
Answer explanation
The sections of a scope statement are project description, key deliverables, success and acceptance criteria, exclusions, time and cost estimates, assumptions, and constraints
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which of the following describes influencers? (select all that apply)
Influencers can impact, change, or create a new constraint.
Scope creep is an example of an influencer.
Change request is an influencer.
Interaction between constraints is an example of an influencer.
Answer explanation
All of the options describe and provide examples of influences
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following involves changing the project or product scope without considering the impacts it will have to the project schedule, budget, and scope statement?
Change request
Scope creep
Stakeholder/management directive
Quality deficiency
Answer explanation
Scope creep involves changing the product or project scope without regard to impacts to the schedule, budget, and/or resources.
KPIs are key performance indicators that help you incrementally monitor project performance
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
There are three primary constraints on most projects.
Your customer, or project sponsor, will stipulate which of the three is the most important to them.
Which three are the typical constraints found on the majority of projects? (Choose three.)
Budget
Team members
Scope
Quality
Time
Answer explanation
They are budget, scope, and time, all of which impact quality
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your sprint is nearing completion.
The product owner reminds you they will not accept the deliverable unless it measures 3 centimeters exactly. If the measurements are off, the next sprint will be delayed, and the entire project could be at risk.
This is an example of which of the following?
Acceptance criteria
Change request
Stability of scope
Product scope description
Answer explanation
This is an example of acceptance criteria for the user story
Create a free account and access millions of resources
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade