PMI PMR Readiness (Exam 1)

PMI PMR Readiness (Exam 1)

9th - 12th Grade

50 Qs

quiz-placeholder

Similar activities

B.M. MID TERM EXAM

B.M. MID TERM EXAM

11th - 12th Grade

45 Qs

Business Management I Mid Term Review (v.2019)

Business Management I Mid Term Review (v.2019)

9th - 12th Grade

50 Qs

Business Management I (Objectives 1.01-1.06)

Business Management I (Objectives 1.01-1.06)

9th - 12th Grade

47 Qs

BM 1 Unit 1 Review

BM 1 Unit 1 Review

9th - 12th Grade

47 Qs

PMP December assessment 2020

PMP December assessment 2020

10th Grade - Professional Development

50 Qs

Business FINAL EXAM

Business FINAL EXAM

12th Grade

50 Qs

Business Mgmt -  REVIEW CH's 1-6 Spring 2023

Business Mgmt - REVIEW CH's 1-6 Spring 2023

9th - 12th Grade

50 Qs

PMI PMR Readiness (Exam 1)

PMI PMR Readiness (Exam 1)

Assessment

Quiz

Business

9th - 12th Grade

Medium

Created by

JASMINE SHEPHERD

Used 15+ times

FREE Resource

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

Two teams working through a project conflict seek a win/win solution. Which conflict strategy should they employ?

Compromise/ Reconcile

Force/ Direct

Collaborate/ Problem-Solve

Smooth/ Accommodate

Answer explanation

To achieve a win/win solution, the teams should collaborate and problem-solve, working together to find a mutually beneficial outcome.

2.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

A construction company wants to follow proper processes for projects and their documentation. Which document serves as the official authorization for a project?

Statement of work

WBS

Project Charter

Project Scope

Answer explanation

The Project Charter serves as the official authorization for a project, outlining the project objectives, scope, stakeholders, and budget.

3.

MULTIPLE SELECT QUESTION

1 min • 2 pts

Which parts of a project plan are interdependent during the planning phase? (Choose three)

Quality

Schedule

Scope

Budget

Acceptance

Answer explanation

During the planning phase of a project, the schedule, scope, and budget are interdependent as changes in one area can impact the others. Quality and acceptance are important but not directly interdependent during the planning phase.

4.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

A project to build a new library is behind schedule. Which adjustment to the project plan will have the best chance of putting the schedule back on track?

Reducing the number of quality inspections on the building.

Adding an additional team of builders to the project.

Removing a task to plant the garden.

Increasing the project budget by 10%

Answer explanation

Removing a task to plant the garden will help put the schedule back on track by reducing unnecessary work and focusing on essential project components.

5.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

A project manager receives a suggestion for an app feature that was not part of the original development scoping. What should be the first step taken to add it to the project scope?

Make the change to the project scope.

Do an impact analysis on the change.

Send the change to the change review board.

Identify a change request,

Answer explanation

Identifying a change request is the first step to add a new feature to the project scope, allowing for proper documentation and evaluation before making any changes.

6.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

A new project manager wants to know why closing contracts is an important part of the closing phase. What is the overall purpose?

To ensure a contract stayed under budget.

To transition a good or service to its maintenance phase.

To ensure work has been completed accurately and satisfactorily.

To see if any scope changes are needed.

Answer explanation

The overall purpose of closing contracts in the closing phase is to ensure work has been completed accurately and satisfactorily.

7.

MULTIPLE CHOICE QUESTION

1 min • 2 pts

Which project is utilizing a predictive approach?

A garden area that has a defined space and number of plants to be planted, but the time frame of the building of the garden is not set.

A science lab to where the specifications of the lab can be defined and adjusted once the core of the lab is built.

A building wing where all of the specifications for the classrooms are defined up front and any changes to the specifications have to go through a change control board.

A playground with multiple areas, each with its own individual project, with multiple fixed scopes, but the overall project is subject to change.

Answer explanation

The project utilizing a predictive approach is the building wing where all specifications for the classrooms are defined upfront, and any changes must go through a change control board.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?