Prestressed Concrete HW 1b

Prestressed Concrete HW 1b

Professional Development

10 Qs

quiz-placeholder

Similar activities

MQA-04

MQA-04

Professional Development

11 Qs

I LOVE MYSELF

I LOVE MYSELF

Professional Development

15 Qs

Literasi DIKTI #3

Literasi DIKTI #3

Professional Development

10 Qs

Fun Quiz - Unit

Fun Quiz - Unit

Professional Development

10 Qs

Labor Relations and Negotations 1

Labor Relations and Negotations 1

University - Professional Development

15 Qs

COVID19 Awareness

COVID19 Awareness

Professional Development

8 Qs

TEL QUIZ

TEL QUIZ

Professional Development

10 Qs

May 2020 Quiz

May 2020 Quiz

KG - Professional Development

10 Qs

Prestressed Concrete HW 1b

Prestressed Concrete HW 1b

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Easy

Created by

Piledriverob Piledriverob2375

Used 14+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Do not start any transition curvature in a Tendon closer than_____ from the stressing Anchorage.

12 INCHES

6 inches

12 inches plus 1

Answer explanation

FIELD MANAUL fig. 4-4

SPECIFICATIONS 3.7.5.3

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Beam Tendons should be supported at a maximum spacing of ?

48 INCHES

24"

13"

Answer explanation

FIELD MANUAL 4.5.2

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Couplers should only be used at locations approved by the _________.

LDP

License

Design

Professional

supervisor

foreman

Answer explanation

FIELD MANUAL 9.10.3

SPECIFICATIONS 2.4.3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Extension cords for stressing equipment at a minimum should be three-wire, 12 gauge & less than ______ in length

100 FEET

50'

1000'

Answer explanation

FIELD MANULA 6.3.(g)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Proper concrete consolidation is most critical at the ___________.

ANCHORAGE ZONE

midspan

entire pour

Answer explanation

FIELD MANUAL 5.1.3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A minimum clear distance of ______ should be maintained between PT Tendons & blocked out openings.

3 INCHES

6 inches plus 1

12 inches

Answer explanation

FIELD MANUAL 4.4.19

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Tape used as a component for sheathing repairs shall have a minimum width of _____.

2 INCHES

1-1/2 inches

6 inches

Answer explanation

SPECIFICATIONS 2.4.3.2

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development