1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

During Sprint Planning, the Development Team realizes they have too much work to complete in the upcoming Sprint. What action should the Scrum Master take?

Extend the Sprint duration

Remove items from the Sprint Backlog

Let the Development Team decide how to handle it

Ask the Product Owner to reprioritize the items

2.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

The Product Owner insists on adding more items to the Sprint Backlog during Sprint Planning. What should the Scrum Master do?

Allow the addition since the Product Owner owns the backlog

Encourage the Product Owner to wait until the next Sprint

Include the items but extend the Sprint duration

Facilitate a discussion with the Development Team to evaluate the impact

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

During the Daily Scrum, a team member reports being blocked by a technical issue. What is the Scrum Master's role?

Solve the technical issue immediately

Assign another team member to help

Encourage the team to address it after the meeting

Escalate the issue to senior management

4.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

In the Daily Scrum, one team member consistently dominates the conversation and others struggle to provide updates. What should the Scrum Master do?

Allow the dominant team member to continue

Interrupt the dominant member and redirect the focus

Extend the Daily Scrum to accommodate everyone

Cancel the Daily Scrum for that day

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

During the Sprint Review, stakeholders express concerns about the quality of the increment. What should the Scrum Master do?

Defend the team and their work

Acknowledge the concerns and work with the team to address them

Ask the stakeholders to provide more detailed feedback later

Interrupt the stakeholders and steer the discussion to other topics

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

In the Sprint Review, the Product Owner is not present to provide feedback on the increment. What should the Scrum Master do?

Proceed with the review without the Product Owner

Delay the Sprint Review until the Product Owner is available

Ask another team member to act as a proxy for the Product Owner

5.    Continue with the review and inform the Product Owner later

7.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

During the Sprint Retrospective, team members are hesitant to voice their concerns openly. What should the Scrum Master do?

Encourage team members to express themselves honestly

Facilitate the retrospective without addressing the hesitancy

Cancel the retrospective and reschedule it for another time

Provide feedback on behalf of the team to maintain transparency

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development