1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Where does the naming SCRUM come from?

American football

Rugby

Soccer

Athletics

Answer explanation

Media Image

Remember the formation from the presentation? It is the scrum in rugby.

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The name of the iteration in SCRUM is ...

PI (product increment)

Scrum

Sprint

Iteration

Answer explanation

Media Image

The name of the iteration is sprint.

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is the difference between the product backlog and the sprint backlog?

Nothing, they are completely the same thing

The sprint backlog is part of the product backlog, but it is changing every day

The sprint backlog is condstructed from the product backlog but it is frozen

They are the same, none of them can be changed

Answer explanation

Media Image

The sprint backlog is a subset of the product backlog commited by the team for the sprint.

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is one of the two main features of the Product Backlog?

Detailed plan about what has to be done in the next sprint

Constantly decreasing until the end of the sprint

Prioritized: business values, dependencies can influence priority

Frozen for the time of the sprint

Answer explanation

Media Image

It is prioritized.

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Can we change the sprint backlog during the sprint?

Yes, but only in certain cases (urgent situations, good progress)

Yes, we can change it on every daily standup

Yes, but only the Scrum Master can change it

Yes, but only the testers can change it

Answer explanation

Media Image

In case there is an urgent situation or the team has finished the tasks, it can be changed or tasks can be added.

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is true for the daily standups?

It is always better to have it virtually on Teams

Maximum 5 minutes

Product Owner is a mandatory participant

Quick status to 3 questions

Answer explanation

Media Image

To ensure transparency every day, the team members answer to 3 questions in 15 minutes.

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is not part of the sprint planning?

Estimating the effort

Understanding the task

Showing what has been done in the next sprint

Writing the tasks for the next sprint

Answer explanation

Media Image

The sprint review is not part of the sprint planning

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?