PMP EXAM PART 9

PMP EXAM PART 9

Professional Development

5 Qs

quiz-placeholder

Similar activities

Project Execution Methodology: Preliminary Contract Activity

Project Execution Methodology: Preliminary Contract Activity

Professional Development

9 Qs

NEOP - Project Management 2024

NEOP - Project Management 2024

Professional Development

10 Qs

Scrum

Scrum

Professional Development

10 Qs

Project Management - Test

Project Management - Test

University - Professional Development

10 Qs

Sprint Planning Quiz MS-DAIS-IO

Sprint Planning Quiz MS-DAIS-IO

Professional Development

10 Qs

PMT Internal Meeting No. 5

PMT Internal Meeting No. 5

Professional Development

10 Qs

Agile the P&T Way - Roles

Agile the P&T Way - Roles

Professional Development

8 Qs

PMP EXAM PART 9

PMP EXAM PART 9

Assessment

Quiz

Other

Professional Development

Hard

Created by

Lovita Lovita

Used 4+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

       You are managing a project that is nearing its end. You have been reviewing the project management plan to ensure that all the project work is completed and that the project has met its objectives. The next thing you need to do before moving on to the next project is to complete the administrative closure of the project.

 

Which of the following activities will not be performed as part of this process?

Closing seller contracts

Handing over the project deliverables to operations

  Transferring the knowledge gained to the lessons learned repository

Measuring stakeholder satisfaction

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You are in the initiation stage of a project that aims to deploy and then maintain the robotics for an automated production line for a returning client. In the project charter, you need to include the agreed mean time to recover (MTTR) in the event of a breakdown.

 

What should you do to find this information?

Do nothing since agreements are not yet available during project initiation

Refer to the procurement management plan

Review any emails or other correspondence with the client

Check the service level agreement with the client

 

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

  During project planning, the project manager creates the project schedule using a Gantt chart. Three Scrum teams will develop the project deliverables. Due to dependencies, the teams will be required to coordinate their work twice a week using extended standup meetings.

 

What should the project manager do next?

Submit a change request to switch the Gantt chart to burndown chart

 

Include Scrum of Scrums (SoS) meetings in the project schedule

Crash the schedule to eliminate the dependencies between the teams

Reflect the actual velocity of the teams in the project schedule

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

    After a few iterations, new features have been requested and added to the project backlog. Senior leadership has provided additional funding and approved a new project timeline. However, a team member mentions that the project charter is no longer in alignment with the updated project backlog.

 

What action should the agile leader take to resolve the issue?

Ask the team member to revise the project charter and submit it to the project sponsor for approval

 

Take ownership of the issue and work with the project sponsor to revise the project charter

Capture the risk of misalignment between the project backlog and the charter in the risk register

Empower the project team members to develop and implement their own project charter

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

As the project manager, you are in the process of developing a draft of a document that authorizes a new software development project. You have reviewed the agreements and both business documents.

 

What else should be done as part of this process?

 

Identify stakeholders and prepare the stakeholder register

 

Study the governance functions and processes to provide guidance and decision making

 

Update the business documents to correct any errors

 

 Review the benefits management plan