Scope Management Quiz

Quiz
•
Professional Development
•
12th Grade
•
Hard
Kate Shealy
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are scope validation techniques in project management?
Risk analysis, stakeholder analysis, and cost-benefit analysis
Benchmarking, brainstorming, and decision trees
Inspections, reviews, and walkthroughs
Quality control, change control, and issue tracking
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Name one scope control method used in project management.
change control
cost control
schedule control
quality control
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is scope validation important in project management?
To minimize stakeholder involvement and communication.
To encourage scope creep and project failure.
To increase project costs and delays.
To prevent scope creep and ensure project success.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are some challenges faced in scope control?
defining clear project objectives, managing scope creep, ensuring effective communication and collaboration among stakeholders, balancing competing priorities, and controlling changes to the project scope
lack of project objectives, scope creep, poor collaboration among stakeholders
insufficient resources, ineffective communication, lack of project management skills
lack of stakeholder involvement, poor project planning, inadequate change management processes
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the scope verification process in project management?
Scope verification is the process of reviewing and approving changes to the project scope.
Scope verification is the process of formalizing acceptance of the project deliverables by the stakeholders.
Scope verification is the process of documenting the project requirements.
Scope verification is the process of monitoring and controlling the project schedule.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which technique is used to validate the scope against the project requirements?
scope validation
scope authentication
scope confirmation
scope verification
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can scope control help in managing project changes?
By delegating scope control to team members.
By ignoring any changes to the project scope.
By defining and controlling what is included and excluded from the project scope.
By allowing unlimited changes to the project scope.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Pertanyaan tentang Proyek RDMP

Quiz
•
10th Grade - University
10 questions
RPMS

Quiz
•
KG - University
15 questions
Project Management Week 3 Quiz

Quiz
•
12th Grade
6 questions
PM03 Project Plannng - Core Project Team

Quiz
•
12th Grade
15 questions
Structure and Analysis of Nursing Knowkedge

Quiz
•
1st Grade - University
9 questions
Lecture 10

Quiz
•
9th - 12th Grade
10 questions
Servicios de Seguridad - Modulo 3

Quiz
•
1st - 12th Grade
10 questions
Formative vs. Summative Assessment

Quiz
•
9th Grade - University
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade