MGSC chapter 7 exam 2

MGSC chapter 7 exam 2

University

30 Qs

quiz-placeholder

Similar activities

The HiLam Cambridge Nationals of IT

The HiLam Cambridge Nationals of IT

1st Grade - Professional Development

30 Qs

ES034 Planning

ES034 Planning

University - Professional Development

25 Qs

PROJECT MANAGEMENT QUIZZ

PROJECT MANAGEMENT QUIZZ

University

25 Qs

Project Management Quiz

Project Management Quiz

University

25 Qs

07 Test - CPM, estimating, scheduling

07 Test - CPM, estimating, scheduling

University

25 Qs

CMT 210 Midterm Study Guide

CMT 210 Midterm Study Guide

University

35 Qs

Facilities Management Event Quiz

Facilities Management Event Quiz

University

25 Qs

Project Management

Project Management

University

25 Qs

MGSC chapter 7 exam 2

MGSC chapter 7 exam 2

Assessment

Quiz

Other

University

Easy

Created by

Cate D'Angelo

Used 4+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is CPM?

  • A network planning method

  • A project schedule

  • The maximum length of time that an activity can be delayed without delaying the entire project

  • A sequence of activities between the start and finish of a program

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a type of information collected by an effective tracking system?

  • Optimistic and pessimistic times

  • Schedule status

risks

open issues

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is LEAST likely to be an option that a project manager would use to alleviate resource problems?

resource breakdown

resource acquisition

resource allocation

resource leveling

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project managers have several options to alleviate resource problems: resource leveling, resource allocation, and __________.

  • resource acquisition

resource risk

resource management

resource finish time

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does CPM stand for?

critical path method

chart precedence management

critical precedence management

critical program method

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager has enough information to estimate the probability that an activity will be completed on schedule with all of the following EXCEPT which one?

completion time

pessimistic time

optimistic time

most likely time

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A good tracking system will monitor open issues, risks, and __________.

schedule status

minimum cost schedule

the risk management plan

pessimistic time

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?