Agile Mindset & Scrum

Agile Mindset & Scrum

Professional Development

15 Qs

quiz-placeholder

Similar activities

PMPrepCast2 1-15

PMPrepCast2 1-15

Professional Development

15 Qs

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT

Professional Development

10 Qs

SG20_Test_S9_CH8&11 Quality & Risk

SG20_Test_S9_CH8&11 Quality & Risk

Professional Development

10 Qs

Project Risk Management 2022

Project Risk Management 2022

Professional Development

10 Qs

2024 PMP Post-Test 20 questions

2024 PMP Post-Test 20 questions

Professional Development

20 Qs

Conflict Resolution

Conflict Resolution

Professional Development

10 Qs

Final Quiz - Assignment

Final Quiz - Assignment

Professional Development

10 Qs

Quiziz Week 2 Day 4

Quiziz Week 2 Day 4

Professional Development

20 Qs

Agile Mindset & Scrum

Agile Mindset & Scrum

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

SG21 PMIIC

Used 14+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An organization just implemented agile and forms a development team where members are not co-located. The organization’s management style is known for setting clearly defined rules and objectives for team members.

What should the agile project manager do to align the team to the desired outcomes?

Arrange an in-person kick-off meeting to improve upon

working relationships.

Discuss options with management that would align

individual goals to project goals.

Schedule a speaker to inspire a collective vision across the

team.

Foster commitment through team engagement and planning.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A new product is being constructed by an agile team, but the team has a limited amount of time to complete it. Due to these circumstances, it is important for the team to sustain collaboration for the duration of the project.

To build team solidarity, what should the project leader do?

Institute protocols for handling sprints in a team meeting.

Facilitate meetings with each member of the team to comprehend project goals.

Confer product progress with team members by utilizing a burndown chart.

Analyze the project map for release of product with team

members.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Members from an agile team have been consistently tardy for stand-up meetings and are not meeting project target dates. The project leader assumes the issue may be difficulty with self-managing tasks within the team.

What action should the project leader take?

Aid the team to construct an agreement amongst them that details coveted behavioral norms.

Convene with the team to review the issues and detail actions to solve them.

Adopt a higher leadership role and set an example for the behavior needed.

Assemble agile and time management training for the team to complete.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A new software system is in progress and is in the user acceptance testing phase. The agile project manager discovers that the IT director is discontent, despite positive feedback from majority of business stakeholders.

What action should the agile project manager take next?

Review preceding project meeting attendance to determine participation by the IT director.

Analyze the requirements that are approved for the project with the IT director.

Request feedback from the IT director during testing of user acceptance.

Collect forthright feedback from the IT director.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a new agile project, there have been hindrances related to budgeting and time management. The remote quality assurance team reported a lengthy defect list following completion of a couple sprints. The project manager concluded that the issues stem from language misinterpretation and not project quality.

What should the project manager do?

Prepare and execute sessions with the full project team to review the list of required tasks and descriptions.

Create a meeting with the quality assurance team and voice concerns regarding the feedback they provided.

Request a financial increase from the change control board (CCB) to employ a quality assurance team locally, as opposed to remote.

Combine the quality assurance team and the development team to complete testing at the conclusion of the project.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a project run by a project manager, a couple of stakeholders have a discrepancy regarding agreed upon measures of one project result.

What next step should the project manager take?

Review and analyze the project requirements document.

Review the approved version of a scope statement.

Organize a gathering with the stakeholders.

Modernize documented project risks and their responses.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A member of a project team at a standup proposes altering a feature due to its popularity in the market. A different team member counters and is concerned about quality user experience regarding the feature.

How can the project manager correct this issue?

Present the product owner the option to place the request in

the product backlog by giving the product owner suggestions.

Utilize a voting system and allow the team to decide which

of the features’ version to apply.

Place the issue in the backlog of the sprint and allow the project team to decide at the next meeting.

Arrange a meeting to make a definitive decision that

includes all stakeholders and the project team.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?