CDM 2015 Principal Designer Duty Holder Quiz

Quiz
•
Architecture
•
Professional Development
•
Hard
Richard Bolton
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who is defined as the principal designer under CDM 2015?
The project manager
The designer with control over the pre-construction phase
The principal contractor
The client
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the pre-construction phase of a project?
The phase when construction work begins on site
The phase when the project is signed-off and handed over to the client
The phase when the project information is gathered
The phase when designers and contractors are selected and the project is planned
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who appoints the principal designer?
The principal contractor
The Health and Safety Executive
The client
The local authority
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is one of the important duties of the principal designer during the pre-construction phase?
Preparing the health and safety file
Assisting the client in the project set up and understanding their duties
Liaising with the principal contractor
Assisting with the construction phase plan
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the responsibility of the principal designer in identifying, eliminating, and controlling risks?
To only identify risks in their own design
To ensure the design team eliminates all risks
To communicate risks to the client
To identify, eliminate, reduce, and control risks in their own design and the overall project design
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the role of the principal designer during the construction phase?
Liaising with the principal contractor and other designers
Assisting the client in the project set up
Preparing the health and safety file
Ensuring designers comply with their duties
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of the health and safety file prepared by the principal designer?
To contain information for the client brief
To contain relevant information for the pre-construction phase
To provide information for the construction phase plan
To ensure the health and safety of anyone carrying out future work on the building
Create a free account and access millions of resources
Similar Resources on Wayground
13 questions
Competitive Tendering Quiz

Quiz
•
Professional Development
10 questions
Built Environment Life Cycle Quiz

Quiz
•
Professional Development
10 questions
LARO 21: Synergy - Tropical Design

Quiz
•
Professional Development
10 questions
FT-Optix Quizz

Quiz
•
Professional Development
8 questions
PROF PRAC_A1

Quiz
•
Professional Development
10 questions
Development Process

Quiz
•
Professional Development
10 questions
SPP DOCUMENTS (201 – 209)

Quiz
•
Professional Development
10 questions
AA ch 1 to 4

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade