CDM 2015 Client Duty Holder Quiz

CDM 2015 Client Duty Holder Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

Planning - Urban Patterns

Planning - Urban Patterns

7th Grade - Professional Development

15 Qs

Elements of Design

Elements of Design

9th Grade - Professional Development

15 Qs

Caring

Caring

KG - Professional Development

10 Qs

Hello Neighbor

Hello Neighbor

Professional Development

7 Qs

your mom

your mom

Professional Development

11 Qs

Landscape Architecture

Landscape Architecture

7th Grade - Professional Development

15 Qs

Building Laws Quiz 3- PD1096

Building Laws Quiz 3- PD1096

KG - Professional Development

15 Qs

Quiz 3 : Project Management

Quiz 3 : Project Management

Professional Development

10 Qs

CDM 2015 Client Duty Holder Quiz

CDM 2015 Client Duty Holder Quiz

Assessment

Quiz

Architecture

Professional Development

Practice Problem

Hard

Created by

Richard Bolton

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is the client according to CDM 2015?

The principal designer

The project manager

The principal contractor

The person having construction work carried out for them

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the pre-construction phase also referred to as?

The construction phase

The design phase

The planning phase

The building phase

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the role of the principal designer in the pre-construction phase?

Managing health and safety in the construction phase

Liaising with the principal contractor

Managing health and safety in the pre-construction phase

Overseeing the completion and handover arrangements

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be included in the client brief?

All of the above

The design direction

The main function and operating requirements of the finished building or structure

The reason for the project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When should the principal contractor be appointed?

After the construction phase begins

During the pre-construction phase

At the end of the project

Before the construction phase begins

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the F10 notification form?

To notify the HSE of project completion

To notify the HSE of any notifiable projects

To notify the HSE of any changes in project plans

To notify the Health and Safety Executive (HSE) of any accidents on site

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for creating the construction phase plan?

The project manager

The client

The principal contractor

The principal designer

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?