36 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

Rhonda was just assigned to be a project manager over a five-year data management project that started last year. What document will help her become familiar with how the project is being executed, monitored and controlled, and closed?

project management plan

project statement of work

quality management plan

project charter

2.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

Alan has just been assigned as the project manager for a software development project his company has been awarded. He has been asked to create the project charter and send it to the project sponsor for approval. The main input he needs to develop the project charter is the project statement of work. What should Alan do to obtain the project statement of work?

He should look in the environmental factors for the statement of work

He should create the project statement of work as the project manager.

He should look in the organizational assets to find the statement of work

He should contact the project sponsor or the customer for the statement of work.

3.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

After discovering that some project work failed to be performed according to plan, a project manager analyzes the situation. She then presents what needs to occur to correct the problems to Austin. Austin requests a change in the project to reduce the probability of negative consequences associated with project risks. What type of change request is Austin making?

corrective action

preventative action

defect repair

lessons learned

4.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

A project manager has discovered that a project is outside the original scope. The project manager has requested a change to bring expected future performance of the project work back in line with the project management plan. What type of change implementation has the project manager requested?

defect repair

corrective action

preventative action

lessons learned

5.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

Jen's company requires her to close out any contracts with outside vendors and perform a lessons learned activity with her team before releasing all resources for other projects. This output is commonly referred to as:

artifacts

closure

termination

6.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

Which activity must happen before a project can officially close?

The project team must be assigned to a new project.

The project manager must plan a celebration.

The project manager must call a formal meeting of all stakeholders

The customer has to formally accept the final product.

7.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

Louise is signing off on the sale agreement paperwork so she can receive payment for the real estate project. What process is Louise undergoing?

project close

project termination

historical information


lessons learned

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?