Search Header Logo

SG21 - Baseline Test 1

Authored by SG21 PMIIC

Professional Development

Professional Development

Used 5+ times

SG21 - Baseline Test 1
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

180 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A junior project manager approaches a senior project manager for information on when to start the project closure process of the project they are handling. What information does the senior project manager require from the junior project manager to offer advice?

All planned work is completed and formal acceptance received
All the deliverables are completed and provided to the customer
All project costs are charged to the customer
All improvements are implemented within the planned time period

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager works at a construction company. The current project is a three year, multimillion-dollar initiative to rebuild a stadium. The first phase of the project has been completed within the three month timeframe and within budget. What should the project manager do next?

Move on to the next phase.
Secure approval from the program manager.
Proceed with the contractual closure of the phase.
Begin the administrative closure process.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Due to budgetary constraints, the program manager requested that the project managers make the best use of the available resources within their projects and prioritize resources over schedule milestones. After visualizing the resource histogram, a project manager found evidence that 80% of their project's resources will be used during the last month of the project. How should the project manager proceed?

Request that activities be fast tracked to make better use of available resources.
Allow some of the current resources to be available for other projects.
Suggest to the program manager that they perform an integrated resource leveling among the projects.
Continue the project execution according to the original plan.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A company is developing a new product that needs to implement nonfunctional security requirements. The product owner is concerned about how the team can ensure the implementation of these nonfunctional requirements. What does the project manager need to do to ensure that the product is compliant with security requirements?

Appoint a security expert as part of the team to review the acceptance criteria.
Send the security requirements to the security department to be implemented.
Discuss the security requirements at the next sprint meeting.
Include the security requirements in the Definition of Done (DoD).

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During the project closing, the project sponsor informs the project manager that one of the deliverables, developed by a contractor, must be transferred to a nonprofit organization at no cost. The procurement documentation states that the property of this deliverable reverts to the contractor once the procurement contract is finished. What should the project manager do?

Add "avoid out of scope agreements during the closure process" to the lessons learned register.
Initiate a change request and execute the integrated change control process.
Consider this transfer as an open issue for the contract department and continue closing the project.
Review the contract agreement with the contractor in order to modify the property of the deliverable.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a steering committee meeting, a senior executive raised a concern that although the key cost parameters are reported to be on track, the project might not be delivering the work that was originally scheduled. What measurement should the project manager use to address this concern?

Cost Variance (CV)
Earned Value (EV)
Schedule Variance (SV)
Planned Value (PV)

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager noticed that one team member is frequently absent from project team meetings. Instead of working on the current project, the team member has been working on a task assigned by their functional manager. What should the project manager do to resolve this issue?

Discuss the resource allocation with the team member's functional manager.
Remove the team member from the project team due to their continued absences.
Record the absences in the team member's performance appraisal.
Ask another team member for input regarding the issue.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?