SG21 - Baseline Test 1

SG21 - Baseline Test 1

Professional Development

180 Qs

quiz-placeholder

Similar activities

Baseline Test 2 SG-21

Baseline Test 2 SG-21

Professional Development

180 Qs

salary and wage

salary and wage

Professional Development

175 Qs

Concept 5 Exam

Concept 5 Exam

Professional Development

185 Qs

Prueba Final

Prueba Final

Professional Development

180 Qs

OPE Parte Común

OPE Parte Común

Professional Development

180 Qs

asset and tracing

asset and tracing

Professional Development

178 Qs

SG20 Baseline 1

SG20 Baseline 1

Professional Development

180 Qs

PMP - Area Avvio

PMP - Area Avvio

University - Professional Development

184 Qs

SG21 - Baseline Test 1

SG21 - Baseline Test 1

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

SG21 PMIIC

Used 5+ times

FREE Resource

180 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A junior project manager approaches a senior project manager for information on when to start the project closure process of the project they are handling. What information does the senior project manager require from the junior project manager to offer advice?
All planned work is completed and formal acceptance received
All the deliverables are completed and provided to the customer
All project costs are charged to the customer
All improvements are implemented within the planned time period

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager works at a construction company. The current project is a three year, multimillion-dollar initiative to rebuild a stadium. The first phase of the project has been completed within the three month timeframe and within budget. What should the project manager do next?
Move on to the next phase.
Secure approval from the program manager.
Proceed with the contractual closure of the phase.
Begin the administrative closure process.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Due to budgetary constraints, the program manager requested that the project managers make the best use of the available resources within their projects and prioritize resources over schedule milestones. After visualizing the resource histogram, a project manager found evidence that 80% of their project's resources will be used during the last month of the project. How should the project manager proceed?
Request that activities be fast tracked to make better use of available resources.
Allow some of the current resources to be available for other projects.
Suggest to the program manager that they perform an integrated resource leveling among the projects.
Continue the project execution according to the original plan.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A company is developing a new product that needs to implement nonfunctional security requirements. The product owner is concerned about how the team can ensure the implementation of these nonfunctional requirements. What does the project manager need to do to ensure that the product is compliant with security requirements?
Appoint a security expert as part of the team to review the acceptance criteria.
Send the security requirements to the security department to be implemented.
Discuss the security requirements at the next sprint meeting.
Include the security requirements in the Definition of Done (DoD).

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During the project closing, the project sponsor informs the project manager that one of the deliverables, developed by a contractor, must be transferred to a nonprofit organization at no cost. The procurement documentation states that the property of this deliverable reverts to the contractor once the procurement contract is finished. What should the project manager do?
Add "avoid out of scope agreements during the closure process" to the lessons learned register.
Initiate a change request and execute the integrated change control process.
Consider this transfer as an open issue for the contract department and continue closing the project.
Review the contract agreement with the contractor in order to modify the property of the deliverable.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a steering committee meeting, a senior executive raised a concern that although the key cost parameters are reported to be on track, the project might not be delivering the work that was originally scheduled. What measurement should the project manager use to address this concern?
Cost Variance (CV)
Earned Value (EV)
Schedule Variance (SV)
Planned Value (PV)

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager noticed that one team member is frequently absent from project team meetings. Instead of working on the current project, the team member has been working on a task assigned by their functional manager. What should the project manager do to resolve this issue?
Discuss the resource allocation with the team member's functional manager.
Remove the team member from the project team due to their continued absences.
Record the absences in the team member's performance appraisal.
Ask another team member for input regarding the issue.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?