Quiz 6 - Project Management

Quiz 6 - Project Management

University

19 Qs

quiz-placeholder

Similar activities

Sugar Academy - Module 1

Sugar Academy - Module 1

University

20 Qs

Lalaland Test

Lalaland Test

University

20 Qs

Mixed  Arki SPP No.2

Mixed Arki SPP No.2

University

15 Qs

Exam - Business and Financial Project Management

Exam - Business and Financial Project Management

University

20 Qs

Quiz Manpro Day 8 Cost Management

Quiz Manpro Day 8 Cost Management

University

15 Qs

Manufacturing Cost

Manufacturing Cost

University

20 Qs

Marginal Costing

Marginal Costing

University

15 Qs

PMP Communication Management

PMP Communication Management

University

20 Qs

Quiz 6 - Project Management

Quiz 6 - Project Management

Assessment

Quiz

Other

University

Hard

Created by

Sergio Monteiro

Used 1+ times

FREE Resource

19 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager must have some work done by an external supplier. This work has a great deal of risk associated with it, and it has become very difficult to find a contractor willing to take on the job. Which of the following types of contract would offer the greatest incentive to the supplier?
Firm fixed price
Cost plus fixed fee
Cost plus percentage of cost as an award fee
Time & Materials

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Purchasing insurance is considered an example of risk:
mitigation
transfer
acceptance
avoidance

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A cost performance index CPI of 0.89 means:
at this time, we expect the total project to cost 89 percent MORE than planned.
when the project is completed we will have spent 89 percent MORE than planned.
the project is only progressing at 89 percent of that planned.
the project is only getting 89 cents out of every dollar invested.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your program manager has come to you, the project manager, for help with a bid for her newest project for a new customer. You want to protect your company from financial risk. You have limited scope definition and don't want to disclose your cost structure to your customer. What is the BEST type of contract to choose?
Fixed price (FP)
Cost plus percent of cost (CPPC)
Time and material (T&M)
Cost plus fixed fee (CPFF)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A schedule performance index SPI of 0.76 means:
you are over budget
you are ahead of schedule.
you are only progressing at 76 percent of the rate originally planned.
you are only progressing at 24 percent of the rate originally planned.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of contract do you not want to use if you do not have enough labor to audit invoices?
Cost plus fixed fee (CPFF)
Time & material (T&M)
Fixed price (FP)
Fixed price incentive fee (FPIF)

Answer explanation

CPFF would involve auditing invoices presented by the vendor to account for the costs incurred.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT an advantage of a fixed price contract?
Less work for buyer to manage
Seller has a strong incentive to control costs
Buyer knows the total price at project starts
Final cost may be more than a cost reimbursable contract because contractors have to increase the price to cover their risk

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?