Quiz 6 - Project Management

Quiz 6 - Project Management

University

19 Qs

quiz-placeholder

Similar activities

Review of Biosafety, Biosecurity and Biorisk Management

Review of Biosafety, Biosecurity and Biorisk Management

University

20 Qs

MIS Chapter 4

MIS Chapter 4

University

20 Qs

MIL QUIZ

MIL QUIZ

12th Grade - University

20 Qs

NMMS MAT 7காலம் சார்ந்த கணக்குகள்

NMMS MAT 7காலம் சார்ந்த கணக்குகள்

University

20 Qs

PLANE TABLE SURVEYING

PLANE TABLE SURVEYING

University

15 Qs

Power Electronics Activity

Power Electronics Activity

University

17 Qs

Materials science

Materials science

University

15 Qs

English Diagnostic 2B

English Diagnostic 2B

University

20 Qs

Quiz 6 - Project Management

Quiz 6 - Project Management

Assessment

Quiz

Other

University

Practice Problem

Hard

Created by

Sergio Monteiro

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

19 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager must have some work done by an external supplier. This work has a great deal of risk associated with it, and it has become very difficult to find a contractor willing to take on the job. Which of the following types of contract would offer the greatest incentive to the supplier?

Firm fixed price
Cost plus fixed fee
Cost plus percentage of cost as an award fee
Time & Materials

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Purchasing insurance is considered an example of risk:

mitigation
transfer
acceptance
avoidance

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A cost performance index CPI of 0.89 means:

at this time, we expect the total project to cost 89 percent MORE than planned.
when the project is completed we will have spent 89 percent MORE than planned.
the project is only progressing at 89 percent of that planned.
the project is only getting 89 cents out of every dollar invested.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your program manager has come to you, the project manager, for help with a bid for her newest project for a new customer. You want to protect your company from financial risk. You have limited scope definition and don't want to disclose your cost structure to your customer. What is the BEST type of contract to choose?

Fixed price (FP)
Cost plus percent of cost (CPPC)
Time and material (T&M)
Cost plus fixed fee (CPFF)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A schedule performance index SPI of 0.76 means:

you are over budget
you are ahead of schedule.
you are only progressing at 76 percent of the rate originally planned.
you are only progressing at 24 percent of the rate originally planned.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of contract do you not want to use if you do not have enough labor to audit invoices?

Cost plus fixed fee (CPFF)
Time & material (T&M)
Fixed price (FP)
Fixed price incentive fee (FPIF)

Answer explanation

CPFF would involve auditing invoices presented by the vendor to account for the costs incurred.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT an advantage of a fixed price contract?

Less work for buyer to manage
Seller has a strong incentive to control costs
Buyer knows the total price at project starts
Final cost may be more than a cost reimbursable contract because contractors have to increase the price to cover their risk

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?