Software Development Process Quiz

Software Development Process Quiz

10th Grade

15 Qs

quiz-placeholder

Similar activities

ICT 9 Q4 M3

ICT 9 Q4 M3

9th Grade - University

15 Qs

Woodshop Safety

Woodshop Safety

9th - 12th Grade

14 Qs

Photoshop GMetrix Units 1 & 2 Review

Photoshop GMetrix Units 1 & 2 Review

10th - 12th Grade

16 Qs

WYA Video Vocabulary 1

WYA Video Vocabulary 1

5th Grade - University

10 Qs

hairstyling quiz

hairstyling quiz

10th - 12th Grade

14 Qs

Hari 3 - Kuis Coding & Perkenalan AI

Hari 3 - Kuis Coding & Perkenalan AI

1st - 12th Grade

10 Qs

SISTEMAS DE REALIMENTACIÓN DE ARTEFACTOS II

SISTEMAS DE REALIMENTACIÓN DE ARTEFACTOS II

10th Grade

20 Qs

Software Development Process Quiz

Software Development Process Quiz

Assessment

Quiz

Instructional Technology

10th Grade

Practice Problem

Medium

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first stage in the waterfall approach?

Analysis

Implementation

Design

Testing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which stage in the waterfall approach involves creating sketches of each screen?

Testing

Implementation

Design

Analysis

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which stage of the waterfall approach is the system created?

Testing

Implementation

Design

Analysis

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When does the client give feedback in the waterfall approach?

Implementation

Design

Analysis

Testing

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main requirement for the waterfall approach?

Clear requirements

Client involvement

Continuous changes

Flexible budget

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main goal of the Agile approach?

No client involvement

Complete project in small phases

No testing required

Deliver project all at once

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the project delivered in the Agile approach?

In stages

All at the end

Without testing

Without client feedback

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?