20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You gave the responsibility of collecting requirement from project stakeholder to four of your team members. After starting the requirement collection process, one of your team members left the job and the requirements could not be compiled properly. Initially, you did not notice this, however, during a product review, a few stakeholders told you that some of the features in the product were not requested by them. Therefore, to verify their comments you review the product requirements and identify the issue.

Scope creep

Scope slippage

Gold plating

Opportunity

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

During the planning phase, you have created the WBS for the work that you are about to complete. However, because of a lack of information you are not able to create the WBS for the rest of the work, so you leave it until you get the correct and detailed information. This is an example of:

Iterative development approach

Improper collecting requirement process

Rolling wave planning

Improper scope statement

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The client informs you that he noticed some parts of the work are not being completed by your team. You ensure him that you will look into it and give a proper response after verifying the facts. Which document will you refer to verify it?

Project scope statement

WBS dictionary

Schedule baseline

WBS

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

As the project manager for a large, complex project, you have been getting complaints from your team, including some of the management team, about all the time being spent on planning. You know that by spending time following the appropriate planning process, you can prevent many problems during execution. This will save time in the later stages of the project. One of the primary complaints you were hearing is related to the time it takes to create the Work Breakdown Structure (WBS). You are explaining the importance of the WBS to your project team members.

Which of the following statements about the WBS is incorrect?

It is a hierarchical decomposition of project work

Planned work contained in the lowest level WBS components are called WBS dictionaries.

The WBS subdivides the project work into smaller, more manageable pieces of work

The WBS organizes and defines the total scope of the project work

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

While finalizing the WBS, you assign each work package to a control account and establish a unique identified for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?

It contains all project work

It authorizes the project manager

It is a hierarchy of project staff

It is a hierarchical breakdown of project resources

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

During the collect requirement process, an influential stakeholder requested a feature which was rejected. During the project execution, you notice that you have an opportunity to incorporate the requirement of this stakeholder into product and it will cost you nothing. By doing so, the stakeholder will be pleased and may help you in your next assignment. This is an example of:

Scope creep

Scope slippage

Gold plating

Opportunity

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

In the the create WBS process, you sub-divide project deliverables and project work into smaller and more manageable components. The output of this process is the Scope Baseline and project document updates. Which of the following truly represents the scope baseline?

Scope statement, Scope management plan, Schedule baseline

Scope statement, WBS, WBS dictionary

WBS, WBS dictionary

Scope statement, WBS, Schedule baseline

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?