Mentoring & Coaching Pertemuan 6 Schedule and Cost POST TEST
Authored by Training eNetwoQ ServIT Indonesia
Professional Development
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
While working on a large building development project the team has identified a particular warehouse they would use to fabricate the steel beams. Where would the team store this information?
Activity List
Activity Attributes
Milestone List
Project Schedule Network Diagram
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following methods is used to construct a schedule in which activities are represented by nodes and are graphically linked?
Precedence diagramming method
Critical path method
Scheduling method
Diagram method
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
While working on a large systems upgrade project, the project team has decided that they can install the servers and the workstations at the same time. The activities will all start at the same time but the workstation installations will take a bit longer to finish. What relationship best describes this scenario?
Finish to start
Start to start
Finish to finish
Start to late finish
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
While working on the network installation project the project team has determined that they must finish the router configurations before they can set up the workstations. The workstations cannot be set up until the router configurations are done. What kind of dependency does this best describes?
Discretionary Dependency
Mandatory Dependency
External Dependency
Physical Dependency
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
The project team has filed for a permit in order to continue building the foundation for a large office building. The permit usually takes about 6 weeks to arrive, and the team is worried it may take even longer. What kind of dependency best describes this scenario?
Internal Dependency
External Dependency
Discretionary Dependency
Physical Dependency
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
The budget manager has completed the earned value analysis for the project. He has concluded that the CPI of the project is .9. Which of the following statements best describes this project?
Over budget 10%
Over budget 90%
On Budget 90%
On Budget 10%
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
The project manager has calculated the EV of the project to be $14,000 and the PV to be $16,000. The BAC is currently at $22,000. Which statement best describes this project?
The Project is ahead schedule
The project is on budget
The project is on schedule
The Project is behind schedule
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?