1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a critical path in the planned work event?
A sequence that is irrelevant to other work
A sequence that may delay other work if not completed
A sequence that is not important in the planned work event
A sequence that is always completed first
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of purging with an inert gas after draining hydrocarbons from piping and vessels?
To remove any remaining hydrocarbons and prevent explosions
To introduce more hydrocarbons into the vessels
To increase the pressure inside the vessels
To cool down the equipment
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be done before allowing entry into vessels during shutdown?
Check the temperature of the vessels
Check the color of the vessels
Check the pressure of the vessels
Check vessels daily for LEL
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be done to prevent pump seal damage during product pump out?
Increase the speed of the pumps
Shutdown mechanical seal pumps immediately before liquid levels are depleted
Allow the pumps to run dry
Use the pumps continuously
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be done when shutting down furnace fires to prevent a firebox explosion?
Leave the firebox open
Close the master valve and keep the burner lighted
Open all valves and turn off the burner
Increase the fuel flow
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be done before steam purging to prevent equipment damage?
Introduce more water into the equipment
Increase the pressure inside the equipment
Drain all water from water-cooled heat exchanger and open the vent
Close all vents
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main purpose of securing equipment during unit clear up?
To prevent accidents and equipment damage
To increase the temperature inside the equipment
To speed up the shutdown process
To allow more feed into the equipment
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?