31 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Single flying shore should have a depth of not less than __________ of the clear span and width of not less than __________ of its length
1/8, 1/9
3/9, 3/8
1/3, 1/5
1/2, 1/1
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the minimum period for the removal of props to beams and arches for a span of 6m in centering / form work?
10 Days
14 Days
17 Days
20 Days
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the approximate depth of vertical sheeting adopted in timbering in soft ground?
10m
12m
15m
17m
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the distance between the (in single row) standards in single scaffolding?
2.0 m
1.7 m
1.5 m
1.2 m
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the depth of trench while box sheeting carried out in timbering in loose soil?
4 m
5 m
5.5 m
6 m
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the maximum suitable distance between the two adjacent parallel walls for single flying shore?
5 m
9 m
15 m
18 m
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The method of timbering of trenches used for supporting the sides of soft ground of depth not exceeding 10m and providing an offset at the end of the each stage is
Box sheeting
Stay bracing
Vertical sheeting
Runner system
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?