SKEMA Elective – Project Management Course – Final TEST

SKEMA Elective – Project Management Course – Final TEST

University

50 Qs

quiz-placeholder

Similar activities

PRAKARYA KELAS 12 SEMESTER 2

PRAKARYA KELAS 12 SEMESTER 2

12th Grade - University

50 Qs

teknologi layanan jaringan

teknologi layanan jaringan

University

45 Qs

SKEMA Elective – Project Management Course – Final TEST

SKEMA Elective – Project Management Course – Final TEST

Assessment

Quiz

Life Project

University

Hard

Created by

Paolino Kitieu

Used 2+ times

FREE Resource

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is a Project?

A project is a  endeavor with a definite timing to create a unique product

A project is a temporary endeavor with a definite timing

A project is a temporary endeavor with a definite timing, to create a unique product

A project is a endeavor with to create a product

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Amount the following which one are part of the Steps to engage stakeholders

Identify - Analyze - Prioritize - recrute

Identify - Call - monitor - Prioritize

Identify - Analyze - Prioritize - monitor

Negotiate - Appreciate - monitor - Prioritize

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

How many Project Performance Domains we have ?

6

8

12

10

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The communication management plan is a document which includes descriptions of

Project level performance reports

Stakeholder communication requirements

Activity level status reports

Responsibility assignments

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project charter is a document that…

…describes both the project scope and the product scope at detail level.

…authorizes the project and the use of organizational resources to meet project requirements.


…breaks down the project scope over several steps to describe the project on work package level.

…describes all activities which are necessary to create the project deliverables.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

In Agile project, Who is ultimately responsible for QUALITY management on the project?

Project engineer

Quality manager

Scrum Master

Team member

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You have just been appointed Project manager on a new project quite similar to few projects you already done. During the planning phase, you manage with the team to collect and analyze most requirements with corresponding schedule, cost, and resources. Which approach is more adequate for you project?

Adaptive Approach

Hybrid Approach

Predictive approach

None of the above

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?