Search Header Logo

PSM 1 - 57 questions

Authored by d t

Computers

Professional Development

Used 2+ times

PSM 1 - 57 questions
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

57 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?

Yes, but only for Scrum Teams whose work has dependencies.
Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
No, each Scrum Team stands alone.
No, that is far too hard and must be done in a hardening Sprint.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When can a Development Team cancel a Sprint?

It can't. Only Product Owners can cancel Sprints.
When functional expectations are not well understood.
When the Product Owner is absent too often.
When the selected Product Backlog items for the Sprint become unachievable.
When a technical dependency cannot be resolved.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

The Sprint Backlog.
The Sprint Goal
The release plan.
Sprint Review minutes.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should a Development Team deal with non-functional requirements?

Ensure every Increment meets them.
Make sure the release department understands these requirements, but it is not the Development Team's responsibility.
Handle them during the Integration Sprint preceding the Release Sprint.
Assign them to the lead developers on the team.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When is a Sprint over?

When the Product Owner says it is done.
When all Product Backlog items meet their definition of ג€Doneג€.
When all the tasks are completed.
When the time-box expires.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

True or False: Scrum has a role called `Project Manager`.

True
False

7.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What are two effective ways for the Scrum Team to make non-functional requirements visible? (Choose two.)

Put them on a separate list on the Scrum board, available for all to see.
Add them to the Product Backlog to ensure transparency.
Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.
Add them to the definition of ג€Doneג€ so the work is taken care of every Sprint.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?