Project Management Quiz

Project Management Quiz

12th Grade

70 Qs

quiz-placeholder

Similar activities

QFS PRETEST

QFS PRETEST

8th - 12th Grade

65 Qs

WordMasters championship FINAL ROUND practice

WordMasters championship FINAL ROUND practice

4th Grade - University

75 Qs

REVIEW HOLIDAYS AND SIMPLE PAST

REVIEW HOLIDAYS AND SIMPLE PAST

9th - 12th Grade

71 Qs

G4 June - July Evaluation

G4 June - July Evaluation

12th Grade

70 Qs

GLOBAL 12 UNIT 5 VOCABULARY

GLOBAL 12 UNIT 5 VOCABULARY

12th Grade

74 Qs

phrasal verb

phrasal verb

9th Grade - University

70 Qs

STEM Review P1 Sem2 Unit 5

STEM Review P1 Sem2 Unit 5

12th Grade

66 Qs

Professional Communications Orientation

Professional Communications Orientation

12th Grade

72 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

English

12th Grade

Hard

CCSS
2.MD.B.5

Standards-aligned

Created by

kainaat jabir

FREE Resource

70 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does CPM calculate in project management?

The weighted average duration estimate

The total duration of the project

The probability of completing the project on time

The risks associated with each activity

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is PERT concerned with when calculating project duration?

The total duration of the project

The risks associated with each activity

The chance of completing the project by a certain duration

The completion time associated with a predetermined level of risk

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should a project manager (PM) determine when analyzing project completion time?

The weighted average duration estimate

The total duration of the project

The probability that a project will be completed by the suggested time

The risks associated with each activity

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the three time estimates used in PERT for calculating completion times?

Optimistic (O), Pessimistic (P), Most likely (M)

Quick (Q), Slow (S), Average (A)

Short (S), Long (L), Expected (E)

Early (E), Late (L), Usual (U)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does Optimistic time (O) represent in PERT calculations?

The maximum possible time required to accomplish a task, assuming everything goes wrong.

The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.

The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.

The best estimate of the time required to accomplish a task, assuming everything proceeds as normal and is the same as Most likely time (M).

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does Pessimistic time (P) signify in PERT calculations?

The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.

The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.

The maximum possible time required to accomplish a task, assuming everything goes wrong.

The average time required to accomplish a task, taking into account the best and worst scenarios.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is Expected time (TE) calculated in PERT?

TE = (O + P) / 2

TE = (O + 4M + P) / 6

TE = (O + M + P) / 3

TE = (4O + 2M + P) / 7

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?