
Project Management Quiz

Quiz
•
English
•
12th Grade
•
Hard
Standards-aligned
kainaat jabir
FREE Resource
70 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does CPM calculate in project management?
The weighted average duration estimate
The total duration of the project
The probability of completing the project on time
The risks associated with each activity
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is PERT concerned with when calculating project duration?
The total duration of the project
The risks associated with each activity
The chance of completing the project by a certain duration
The completion time associated with a predetermined level of risk
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should a project manager (PM) determine when analyzing project completion time?
The weighted average duration estimate
The total duration of the project
The probability that a project will be completed by the suggested time
The risks associated with each activity
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are the three time estimates used in PERT for calculating completion times?
Optimistic (O), Pessimistic (P), Most likely (M)
Quick (Q), Slow (S), Average (A)
Short (S), Long (L), Expected (E)
Early (E), Late (L), Usual (U)
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does Optimistic time (O) represent in PERT calculations?
The maximum possible time required to accomplish a task, assuming everything goes wrong.
The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.
The best estimate of the time required to accomplish a task, assuming everything proceeds as normal and is the same as Most likely time (M).
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does Pessimistic time (P) signify in PERT calculations?
The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.
The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
The maximum possible time required to accomplish a task, assuming everything goes wrong.
The average time required to accomplish a task, taking into account the best and worst scenarios.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is Expected time (TE) calculated in PERT?
TE = (O + P) / 2
TE = (O + 4M + P) / 6
TE = (O + M + P) / 3
TE = (4O + 2M + P) / 7
Create a free account and access millions of resources
Similar Resources on Wayground
75 questions
English I: Midterm Review

Quiz
•
9th Grade - University
65 questions
Unit 1: Exploring Work Vocabulary

Quiz
•
12th Grade - University
70 questions
phrasal verb

Quiz
•
9th Grade - University
71 questions
REVIEW HOLIDAYS AND SIMPLE PAST

Quiz
•
9th - 12th Grade
66 questions
Quiz latihan 3 bab

Quiz
•
8th Grade - University
70 questions
ECCE Grammar and vocabulary quiz

Quiz
•
11th Grade - Professi...
69 questions
G7 - ÔN TẬP CUỐI KÌ 1 (U6 + Review)

Quiz
•
11th Grade - University
70 questions
QUESTION TAGS AND INDIRECT QUESTIONS

Quiz
•
9th - 12th Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade