Transformation of Demand into Supply (BSCM)
Authored by Công Lâm
Mathematics
1st - 5th Grade
CCSS covered
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Lot-for-lot ordering rules based on net requirements will:
Order based on supplier preferences
Order in fixed intervals
Order only the amount needed
Order net requirements plus safety stock
Answer explanation
Lot-for-lot ordering rules will order just the amount needed based on the net requirements.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Quick setup and changeover enhances customer satisfaction levels. All of the following are competitive advantages created by quick changeovers EXCEPT:
Reduced work in process
Improved quality
Improved maintenance
Reduced span times
Answer explanation
While improved maintenance is usually necessary for improved changeover, it is not created by quick setup. Improved flow, reduced lead and span times, and improved quality are all benefits of quick changeover and setup.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following is true in regards to priority?
It involves maintaining the correct due dates on orders
It involves the accuracy of the forecast to meet demand
It refers to capacity requirements and production schedules
It refers to vendor due dates of incoming materials
Answer explanation
Priority refers to the system’s ability to maintain the true due dates for orders. Planning systems constantly evaluate the true due dates for released orders and will expedite or reschedule out the orders.
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following best describes the concept of capacity?
The amount of standard hours earned
The volume of inventory created
The rate of doing work
The quantity of work performed
Answer explanation
Capacity is concerned with the rate of doing work. The APICS dictionary defines capacity as the capability of a worker, machine, work center, plan, or organization to produce output per period of time.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A message to the planner regarding a problem that needs attention is known as a(n):
Error indication
Exception message
Acceptance notification
Order exception
Answer explanation
An exception message provides the planner with a notice that a problem needs attention. These exceptions could be late orders, orders not needed, order rescheduling, and several other factors.
Tags
CCSS.RI.2.5
CCSS.RI.3.5
CCSS.RI.4.5
CCSS.RI.5.3
CCSS.RI.5.5
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A machining operation utilizes five machines working 14 hours a day, five days per week. What is the weekly available time?
350
400
300
250
Answer explanation
Available time is calculated by multiplying the number of machines (5) by the number of hours they are available each day (14) by the number of days each week (5). The result would be 14 x 5 x 5, or 350.
Tags
CCSS.8.EE.C.7B
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A work cell has 275 hours per week of available time with a utilization rate of 80%. How many hours are actually being spent producing parts?
120
200
220
55
Answer explanation
Utilization rate measures the percentage of time the machines are actually producing parts. The hours actually worked can be calculated by multiplying the utilization percentage (80%) by the number of hours available (275), which equals 220 hours.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?