PM FSB
Quiz
•
Science
•
University
•
Practice Problem
•
Medium
Nguyen Chi Hieu
Used 5+ times
FREE Resource
Enhance your content in a minute
160 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is an input to the Develop Project Management Plan process
The project charter
The enterprise environmental factors
The enterprise environmental factors
The organization's processes and procedures
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the auction, you see an auctioneer who is your close friend. What should your next step be?
During the auction, you see an auctioneer who is your close friend. What should your next step be?
During the auction, you see an auctioneer who is your close friend. What should your next step be?
You will try not to give him the contract to prove your integrity
You will resign immediately from the tender process
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a project to build five bridges. The project consists of five sequential phases with each phase delivering one bridge. After the first phase of the project is complete, which process group of the second phase should follow?
Planning
Closing
Initiating
Executing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project aims to investigate the feasibility of constructing a hydroelectric dam from a technical, economic, and social point of view. The project charter created by the project manager on behalf of the project sponsor is now approved. Which of the following processes should be performed next?
Identify Stakeholders
Develop Project Management Plan
Develop Project Charter
Identify Risks
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project sponsor asks for a copy of the document that contains the description, owner, source, priority, and status of product requirements. Which project document is the project sponsor requesting?
The scope management plan
The requirements traceability matrix
The work breakdown structure (WBS)
The requirements management plan
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Development is a critical aspect in a project with large size and regulatory and environmental considerations. What is the first thing you should do as a starting point for initial project planning?
Share project scope with the involved team to establish common understanding about project deliverables
Share project scope with the involved team to establish common understanding about project deliverables
Share project scope with the involved team to establish common understanding about project deliverables
Hold a project kick-off meeting with the aim to inform and engage stakeholders and obtain commitment
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company sets up a change control board (CCB) dedicated to the purpose of reviewing and evaluating the changes submitted for all projects. Which of the following best describes an individual or group that can request a change on a project in a situation where the project sponsor is a member of the CCB?
Project sponsor
Project manager
Any stakeholder
Project team
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade