Project evaluation Quiz - ITPM L9 Activity

Project evaluation Quiz - ITPM L9 Activity

University

13 Qs

quiz-placeholder

Similar activities

Adopt me

Adopt me

KG - Professional Development

14 Qs

Listen in Python

Listen in Python

University

10 Qs

ITESA Roadmap Event 12-09-24

ITESA Roadmap Event 12-09-24

University

10 Qs

Innovative or Not

Innovative or Not

KG - University

12 Qs

The importance of Being Earnest

The importance of Being Earnest

KG - University

11 Qs

Evaluasi Pertemuan 12 DRPL TI-3B

Evaluasi Pertemuan 12 DRPL TI-3B

University

15 Qs

STM 1042- AKSES ELEKTRONIK

STM 1042- AKSES ELEKTRONIK

7th Grade - University

10 Qs

Cryptography

Cryptography

6th Grade - University

15 Qs

Project evaluation Quiz - ITPM L9 Activity

Project evaluation Quiz - ITPM L9 Activity

Assessment

Quiz

Computers

University

Practice Problem

Medium

Created by

Jerry Jackson Bent

Used 23+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

13 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What 3 factors should be considered in the project evaluation process?

  • Cost

Project methodology

  • Timeline

  • Customer satisfaction

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Before measuring project success, you need a clear understanding of what?

Team and cost

Objectives, scope, and timeline

Quality, time and methodology

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to the article, a well-defined project scope helps you do what?

End a project

Hire teams

set realistic expectations

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When measuring project success, what step enables you to identify potential issues early and make necessary adjustments?

Assess the current status

Define the purpose

Invest in more resources

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do you analyze the results achieved by the project so far

By identifying potential issues early

By communication with your team

By looking at the results achieved against the project goals

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the full meaning of KPI?

Key Performance indicators

Key Portfolio Indicator

Key Performance index

7.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Develop a risk management plan that includes strategies for mitigating or ________ these risks [OPTIONS: Moving, Removing, Transferring]

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?