MP SM IDL 2024

MP SM IDL 2024

University

19 Qs

quiz-placeholder

Similar activities

DI (EM24) - Diseño de Contenidos (T8)

DI (EM24) - Diseño de Contenidos (T8)

University - Professional Development

20 Qs

ระบบปฏิบัติการ ชุดที่ 1

ระบบปฏิบัติการ ชุดที่ 1

University

15 Qs

Internet

Internet

5th Grade - Professional Development

20 Qs

C++ Bootcamp 2k24

C++ Bootcamp 2k24

University

20 Qs

IoTcon

IoTcon

University

15 Qs

OPERATING SYSTEM (QUIZ #1)

OPERATING SYSTEM (QUIZ #1)

University

20 Qs

OOAD Unit 4 : กระบวนการวิเคราะห์และออกแบบเชิงวัตถุ

OOAD Unit 4 : กระบวนการวิเคราะห์และออกแบบเชิงวัตถุ

University

20 Qs

Jaringan Nirkabel dan Kabel Kelas 11 Ganjil

Jaringan Nirkabel dan Kabel Kelas 11 Ganjil

University

20 Qs

MP SM IDL 2024

MP SM IDL 2024

Assessment

Quiz

Computers

University

Medium

Created by

Indra Lukmana

Used 3+ times

FREE Resource

19 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Suppliers and concerned citizens are examples of which type of stakeholders?

Internal

External

supportive

unsupportive

2.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

What type of information about stakeholders is not included in a stakeholder register?

identification

classification

assessment

engagement level

3.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

What type of grid can categorize stakeholders based on their level of authority and concern?

a power/interest grid

an authority/interest grid

an authority/concern grid

a resistance/support grid

4.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

a project stakeholders has high amount of authority & a high amount of interest. relationship?

keep informed

keep satisfied

manage closely

monitor

5.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

type of matrix can help clarify which knowledge areas are most important to stakeholders

a knowledge area matrix

a prioritization matrix

an expectations management matrix

a stakeholder management matrix

6.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

What tool can you use to document, monitor, and track items that need resolution on a project

an issue log

a risk register

an issue register

a resolution log

7.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

When should you start controlling stakeholder engagement on a project?

in the early phases

in the latter phases

in the middle phases

none of the above; you cannot control stakeholder engagement

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?