1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following tasks are typically performed by Product Owners (POs) and Product Management during day one of PI Planning?

Reviewing draft PI plans and providing feedback

Conducting support team breakouts

Communicating the Vision

Collaborating to decompose Features into Stories

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During PI Planning – day one, what is one of the primary tasks performed by Product Owners (POs) and Product Management?

Communicating the Vision

Reviewing draft PI plans and providing feedback

Conducting support team breakouts

d) Negotiating scope

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During PI Planning, what is the purpose of Product Management presenting the top 10 Features to the team?

To surprise the team with new Features

To serve as an input to the planning process

To limit the team's ability to plan and commit to a course of action

To determine the capacity limitations of the team

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important for Product Management to socialize Features before PI Planning?

To limit transparency

To prevent the ART from pulling more Features than necessary

To develop right-sized Features and maintain transparency

To avoid sharing information with the team

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of team breakouts during PI Planning?

To provide support to Product Management

To lead the planning process for upcoming Iterations

To work on planning how to deliver Features in upcoming Iterations

To discuss the Vision and objectives for the ART

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the four things that can be done during the management review and problem-solving meeting at the end of day one of PI Planning?

Presenting draft plans, potential risks, and dependencies

Introducing changes to the schedule or activities for the day

Changing priorities, adjusting Vision, changing scope, and moving people

Facilitating the review of draft plans and PI Objectives

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who facilitates the management review and problem-solving meeting at the end of day one of PI Planning?

The Product Management team

The Release Train Engineer (RTE)

The Agile Teams

The Scrum Master

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?