1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly affect the project schedule. What should the project manager do next?

Validate the information and update the risk management plan.

Update the risk register and discuss it with the project stakeholders.

Source second-hand equipment in order to prepare for any delivery delays.

Update the sponsor of the potential issue and ask for any suggestions.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.

What key activity is needed to ensure the project's success?

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are starting to write your project charter with your project sponsor when the senior managers ask for a time and cost estimate for the project. You have not yet gathered many of the project details. What kind of estimate can you give?

Analogous estimate

Rough order of magnitude estimate

Parametric estimate

Bottom-up estimate

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager has just finished the risk response plan for a $387,000 engineering project. Which of the following should he probably do next?

Determine the overall risk rating of the project.

Begin to analyze the risks that show up in the project drawings.

Add work packages to the project work breakdown structure.

Hold a project risk review.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your team is designing a packaging robot for a pharmaceutical production line. The product owner is an engineer, and he tells you it's a waste of the team's time to create a risk-adjusted backlog. You reply that this tool will allow the team to:

Maximize the expected monetary value of the key product features.

Deliver the highest-value features while mitigating the most serious threats.

Balance continuous improvement with progressive elaboration.

Calculate the contingency reserve needed for all the opportunities and threats.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is quantifying risk for her project. Several of her experts are off-site, but wish to be included. How can this be done?

Perform Monte Carlo analysis using the internet as a tool.

Apply the critical path method.

Determine options for recommended corrective action.

Use facilitation techniques.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project team is creating a project management plan when management asks them to identify project risks and provide some form of qualitative output as soon as possible. What should the project team provide?

Risk triggers

Prioritized list of risks

Contingency reserves

Probability of achieving the time and cost objectives

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?