Push System Versus Pull System Quiz
Quiz
•
Specialty
•
12th Grade
•
Practice Problem
•
Hard
Nurhana Juraimi
FREE Resource
Enhance your content in a minute
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a characteristic of a Push System?
Instructions come from a central planning area
Receiving workstation does not accept any defective parts
Processes are based on customer demand
Quick Changeovers : Set-Up Kaizen
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a characteristic of a Pull System?
What to build and in what order come from a central planning area
Everyone’s work is scheduled and triggered by required start dates
Receiving workstation does not accept any defective parts
Cellular Manufacturing : Flow Kaizen
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main identifier of pull systems?
Having KANBAN methods in production cycle
Receiving workstation does not accept any defective parts
Low Variability :Variability Reduction Kaizen (6 Sigma tools)
Instructions come from a central planning area
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the concept behind a Pull System?
Receiving workstation does not accept any defective parts
Quick Changeovers : Set-Up Kaizen
Instructions come from a central planning area
Processes are based on customer demand
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a prerequisite of a Kanban 'Pull' System?
What to build and in what order come from a central planning area
Receiving workstation does not accept any defective parts
Stable, Flat Demand : JIT Principles
Quick Changeovers : Set-Up Kaizen
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the aim of having a visual aid like Kanban in a Pull System?
To have a lot of paperwork
To build excessive stock levels of raw materials
To reduce lead times and associated costs
To increase paperwork and computer transactions
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What dictates the production requirements for upstream operations in a Pull System?
The Quick Changeovers : Set-Up Kaizen
The anticipated demand
The central planning area
The status of downstream operations
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade