Spec 1_Quiz 2

Spec 1_Quiz 2

University

15 Qs

quiz-placeholder

Similar activities

Quiz on Quantity Surveying

Quiz on Quantity Surveying

University

10 Qs

Revit - Modifying Components

Revit - Modifying Components

9th Grade - University

16 Qs

CONSTRUCTION PRE-PLANNING QUIZ

CONSTRUCTION PRE-PLANNING QUIZ

University

20 Qs

FBC: Introduction to FBC

FBC: Introduction to FBC

University

12 Qs

SITE VISIT QUIZ

SITE VISIT QUIZ

University

10 Qs

4) Building Economics and certificates

4) Building Economics and certificates

University

10 Qs

Construction Technology

Construction Technology

University

20 Qs

Project Delivery

Project Delivery

University

18 Qs

Spec 1_Quiz 2

Spec 1_Quiz 2

Assessment

Quiz

Architecture

University

Medium

Created by

Aira Altovar

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT a typical project delivery method in construction management?

Owner-Supplier Negotiation

Design-Bid-Build

Design-Build

Construction Management at Risk

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which document outlines the legal relationship between the owner and the contractor?

Scope of Work

Change Order

Contract

Request for Proposal (RFP)

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the purpose of a punch list in construction management?

To list all the tools required for the project

To list all the stakeholders involved in the project

To track the progress of the project on a daily basis

To identify incomplete or deficient work that needs to be corrected

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

In construction management, what does the term "change order" refer to?

A request for additional funding by the contractor

A formal meeting to discuss project progress

A change in the project manager overseeing the construction

Alterations to the project scope, schedule, or budget

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the primary objective of the Theory of Constraints (TOC) in management?

Maximizing profits

Identifying and managing constraints

Minimizing costs and conflicts

Increasing production speed

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT typically considered a risk in construction management?

Weather conditions

Labor shortages

Stakeholder satisfaction

Material availability

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is one of the primary responsibilities of a construction manager?

Overseeing the construction process to ensure timely completion

Designing architectural blueprints

Handling financial transactions for the project

Managing the marketing of the construction project

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?