Schedule Management Processes

Authored by Afghanistan Center

Professional Development

4th Grade

Used 1+ times

Schedule Management Processes
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a new telecommunications project, the project manager is tasked with creating a detailed plan that outlines how the project schedule will be developed, managed, and controlled throughout the project lifecycle. Which schedule management process is the project manager performing?

Define Activities

Develop Schedule

Develop Schedule Management Plan

Control Schedule

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the initial planning phase of a construction project, the project manager is listing all the specific tasks that need to be completed to construct a new office building. Which schedule management process does this activity belong to?

Develop Schedule

Define Activities

Sequence Activities

Estimate Activity Durations

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a healthcare IT project, the project manager is arranging the identified tasks in the order they need to be performed, considering dependencies and constraints between them. Which schedule management process is the project manager using?

Develop Schedule

Control Schedule

Sequence Activities

Define Activities

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While planning a marketing campaign, the project manager is estimating how long each task will take to complete based on the resources available and past project data. Which schedule management process is being performed?

Develop Schedule

Define Activities

Estimate Activity Durations

Sequence Activities

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a software development project, the project manager integrates activity durations, dependencies, and resource availability into a comprehensive project timeline. Which schedule management process is this?

Control Schedule

Develop Schedule

Sequence Activities

Define Activities

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the execution phase of a large-scale engineering project, the project manager discovers that several tasks are not progressing as planned and are causing delays. To bring the project back on track, the project manager adjusts the schedule and reallocates resources. Which schedule management process is being applied?

Define Activities

Sequence Activities

Control Schedule

Develop Schedule

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In an agricultural project, the project manager is creating a detailed plan to identify, sequence, and estimate the duration of all activities required to achieve the project objectives. This plan will also define the scheduling methodology and tools that will be used. Which schedule management process is being described?

Define Activities

Develop Schedule Management Plan

Sequence Activities

Estimate Activity Durations

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?