Schedule Compression & Optimization

Schedule Compression & Optimization

4th Grade

8 Qs

quiz-placeholder

Similar activities

Risk Response Strategies - Negative Risks

Risk Response Strategies - Negative Risks

4th Grade

6 Qs

Cost Management Terminology

Cost Management Terminology

4th Grade

8 Qs

ASP-SM-Fmk

ASP-SM-Fmk

KG - University

7 Qs

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

Team Development Stages

Team Development Stages

4th Grade

7 Qs

Maslow's Hierarchy

Maslow's Hierarchy

4th Grade

7 Qs

Organizational Structures

Organizational Structures

4th Grade

7 Qs

Project Data

Project Data

3rd Grade - University

10 Qs

Schedule Compression & Optimization

Schedule Compression & Optimization

Assessment

Quiz

Professional Development

4th Grade

Hard

Created by

Afghanistan Center

Used 8+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a construction project for a new office building, the project manager discovers that the project is behind schedule due to unforeseen delays in obtaining permits. To meet the original deadline, the project manager decides to start the interior design phase before the exterior construction is fully completed, which increases the risk of rework. What schedule compression technique is being used?

Fast Tracking

Crashing

Resource Leveling

Lead Time Adjustment

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During an IT system implementation project, the project team realizes they are falling behind schedule. The project manager decides to add more skilled programmers to the critical path tasks to speed up the coding and testing processes, although this increases the project costs. Which schedule compression technique is being applied?

Fast Tracking

Crashing

Resource Smoothing

Parallel Tasking

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a marketing campaign project, the project manager notices that the deadline is approaching faster than anticipated. To accelerate progress, the project manager opts to conduct market research and content creation simultaneously, even though this might lead to some inconsistencies. Which schedule compression technique does this describe?

Crashing

Fast Tracking

Lead Time Reduction

Concurrent Engineering

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A healthcare project to develop a new medical device is running behind schedule. To recover lost time, the project manager decides to pay overtime to key team members and bring in additional consultants to help with the design and testing phases. This approach significantly increases project costs but helps meet the deadline. What schedule compression technique is being used?

Resource Optimization

Fast Tracking

Crashing

Schedule Re-Baselining

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In an agricultural project aimed at developing a new irrigation system, the project manager faces a tight deadline due to seasonal constraints. The manager decides to overlap the procurement of materials with the initial construction phases, despite the risk of delays if materials are not delivered on time. Which schedule compression technique is this?

Crashing

Fast Tracking

Buffer Management

Schedule Re-Baselining

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A banking software project is at risk of missing its launch date due to delays in the development phase. To accelerate the schedule, the project manager decides to allocate additional funds to hire more developers and testers, increasing the project's cost but ensuring that critical tasks are completed more quickly. Which schedule compression technique is being applied?

Fast Tracking

Crashing

Parallel Tasking

Resource Leveling

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a health project to expand a hospital's capacity, the project manager notices that several critical tasks are scheduled to occur simultaneously, requiring more resources than are available. The project manager decides to adjust the project schedule to ensure that resources are allocated more evenly over the project duration, even if it extends the project timeline. Which technique is the project manager using, and how is it being applied?

Resource Smoothing; Allocating resources without changing the project timeline

Resource Optimization; Maximizing resource efficiency without altering the critical path

Resource Leveling; Adjusting the schedule to balance resource demand with availability

Resource Allocation; Assigning additional resources to critical tasks

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a software development project for a new hospital management system, the project manager identifies that some non-critical tasks have resources allocated that exceed availability. To prevent resource overallocation while maintaining the original project timeline, the project manager adjusts the resource assignments and reassigns non-critical tasks to periods with lower resource demand. Which technique is being used, and what is its primary benefit?


Resource Leveling; Extending the project timeline to meet resource demands

Resource Optimization; Balancing resource assignments without altering the project timeline

Resource Allocation; Adding more resources to the project

Resource Smoothing; Ensuring consistent resource usage without affecting critical path tasks