Risk Management

Risk Management

Vocational training

14 Qs

quiz-placeholder

Similar activities

Quiz on Mitigation and Acceleration

Quiz on Mitigation and Acceleration

University - Professional Development

10 Qs

CRISC Domain 2 MCQ

CRISC Domain 2 MCQ

Professional Development

16 Qs

11. Risk Management

11. Risk Management

1st - 3rd Grade

12 Qs

Risk 10 soal (Chapter 11)

Risk 10 soal (Chapter 11)

Professional Development

10 Qs

BSBOPS403 - Risk Management

BSBOPS403 - Risk Management

Professional Development

15 Qs

Cost Planning Quiz_Day2

Cost Planning Quiz_Day2

12th Grade

18 Qs

AS Risk Management

AS Risk Management

University - Professional Development

15 Qs

BSBWHS519

BSBWHS519

KG - University

10 Qs

Risk Management

Risk Management

Assessment

Quiz

Professional Development

Vocational training

Hard

Created by

Pusilkom Training

FREE Resource

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following risk events is MOST likely to interfere with attaining a project’s schedule objective?

Delays in obtaining required approvals

Substantial increases in the cost of purchased materials

Contract disputes that generate claims for increased payments

Slippage of the planned post-implementation review meeting

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Risks are identified during _________ risk management process(es).

Identify Risks

Perform Qualitative Risks and Monitor Risks

Identify Risks and Perform Quantitative Risks

Identify Risks and Monitor Risks

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Outputs of the Plan Risk Responses process include:

Residual risks, fallback plans and contingency reserves

Risk triggers, contracts and a risk list.

Secondary risks, process updates and risk owners

Contingency plans, project management plan updates, and change requests.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk management activities. For remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also these 2 risks cannot be outsourced or removed from project scope. What is the best solution?

Accept the risk

Mitigate the risk

Avoid the risk

Transfer the risk

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Under which of the following scenarios would you not use a decision tree?

 

When some future scenarios are unknown

When the future scenarios are known

When you need to look at the implications of not choosing certain alternatives

When the outcomes of some of the actions are uncertain

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not an appropriate method for dealing with a negative risk?

Avoid

Transfer

Mitigate

Exploit

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project risks should be identified by:

Those invited to the risk identification process only

Key project stakeholders only

The project manager only

All project personnel

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?