1. A project manager may use different kinds of leadership styles. When will he most likely use a directive leadership style?
a) During the realisation phase
a) During the whole project
a) At the start of the project
a) During project closure
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is a project called which is aimed at achieving an independent result?
Work project
Product project
Concept project
Programme project
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are asked to help choosing a project manager for a technological research and development project. There are four candidates for the position. Natalie is a good project manager; Thomas is the best engineer you have ever met; Greta is familiar with project management, general management and development; Marc is an experienced general manager. Whom should you choose?
Greta
Thomas
Natalie
Marc
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An auditor advises the project manager that two of his team members are developing different software applications with the same function. What might be the most likely reason for this situation?
The matrix structure of the organisation
A badly defined work breakdown structure
Ambiguous wording of the project charter
A lack of cooperation between the team members
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The team building process always follows similar phases, regardless of what kind of team it is. These phases are…?
Forming - Storming - Norming - Performing
Education - Structuring - Leadership - Dislocation
Introduction - Consolidation - Leadership - Performance
Introduction - Development - Problem - Solution
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the proposed elements is not an essential aim of communication?
Accepting the budget
Transmitting information
Creating favourable conditions for motivation
Interaction among the stakeholders
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the proposed elements is not an essential aim of communication?
Accepting the budget
Transmitting information
Creating favourable conditions for motivation
Interaction among the stakeholders
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
72 questions
EXAMENES PSI DES
Quiz
•
University
70 questions
b2-beginner
Quiz
•
University
75 questions
ME-Educ 10
Quiz
•
University
70 questions
Tâm Lý Học Chương 1
Quiz
•
University
70 questions
Passages 1 Units Review 1-5
Quiz
•
University
76 questions
Tallest, Biggest, Longest, Largest, Highest..........
Quiz
•
1st Grade - Professio...
70 questions
T1(NEW). HISTORIA DE LA ARITMÉTICA Y EL ÁLGEBRA
Quiz
•
University
70 questions
OCI 2025
Quiz
•
6th Grade - University
Popular Resources on Wayground
20 questions
Halloween Trivia
Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Order of Operations
Quiz
•
5th Grade
20 questions
Halloween
Quiz
•
5th Grade
16 questions
Halloween
Quiz
•
3rd Grade
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
20 questions
Possessive Nouns
Quiz
•
5th Grade
10 questions
Halloween Traditions and Origins
Interactive video
•
5th - 10th Grade