23 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following does not form part of the commissioning process?

Soundness testing

Visual inspection

Flushing the system

Fitting plumbing appliance

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following parts of the Building Regulations deals with building structure?

Part A

Part B

Part F

Part L

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does LCS stand for?

Long Coil Strand

Low Carbon Steel

Low Copper Steel

Loose Cover Sheet

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following should be used to protect the area you are working in?

Safety shoes

Plywood

Dust sheets

Heat mat

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following is the correct horizontal clipping interval for 15mm copper tube?

1.2m

1.5m

1.8m

2.0m

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At what point should an inhibitor be added to a central heating system during commissioning?

During the first flush

Before flushing

During the final fill of the system

Before cleaning the pipework

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Which one of the following types of screw is shown in the image below?

Phillips

Pozidrive

Slotted

Mirror

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Education