1. A change has been requested by the project team to fix a problem by bringing the future
performance of the project in line with the project management plan. Such a change request is
called __.
a. Corrective action
Submitted change request
Preventive action
d. Supportive action
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following documents is not used as an input for the scope validation process? Select one:
The requirements traceability matrix, which links requirements to their origin and tracks them throughout the project lifecycle.
The verified deliverables, completed and verified for correctness by the quality control process.
The project management plan, which contains the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.
The responsibility assignment matrix, which describes the responsibilities for correcting the scope in case the client rejects the project deliverables.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Nancy is the Project Manager of an overpass project. The project is 18% complete. The Steering Committee will meet tomorrow. She is looking at the schedule forecasts for all of the following except: Select one:
to find out how much more the project will cost.
to identify any necessary change requests.
to determine if the project is within the defined schedule tolerance ranges.
to find out how much the schedule is delayed.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The expected cost necessary to complete the remaining work for a schedule activity, work breakdown structure component, or the project. This is the description of which of the following terms:
Schedule Performance
Cost Performance Index
c. Estimate to Complete
Estimate at Completion
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The final performance report of a project that was completed 6 months late shows the Cost Performance Index (CPI) as 0.83. What is the Schedule Performance Index (SPI) of this project?
SPI = 1.00
SPI = 0.83
SPI = 0.50
Cannot be determined with the given information
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The results of the Risk Response Planning process include:
Secondary risks, process updates, and risk owners
Contingency plans, project management plan updates, and sensitivity analysis
Risk triggers, contracts, and a risk list
Residual risks, contingency plans, and contingency reserves
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the best method to control changes in the project? Select one:
Make changes quickly when they occur
Direct changes to the change control board (CCB)
Prevent changes from being made
Look for sources of changes
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade