PMP Exam Prep Quiz

PMP Exam Prep Quiz

Professional Development

61 Qs

quiz-placeholder

Similar activities

VT7_Telemarketing

VT7_Telemarketing

University - Professional Development

62 Qs

Unit 18

Unit 18

Professional Development

60 Qs

Permanent Waving

Permanent Waving

11th Grade - Professional Development

63 Qs

OP ppl

OP ppl

Professional Development

61 Qs

61-1

61-1

Professional Development

60 Qs

PMP Exam Prep Quiz

PMP Exam Prep Quiz

Assessment

Quiz

Specialty

Professional Development

Medium

Created by

EDUARDO CAMPOS

Used 2+ times

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

61 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. A change has been requested by the project team to fix a problem by bringing the future

performance of the project in line with the project management plan. Such a change request is

called __.

a. Corrective action

Submitted change request

Preventive action

d. Supportive action

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following documents is not used as an input for the scope validation process? Select one:

The requirements traceability matrix, which links requirements to their origin and tracks them throughout the project lifecycle.

The verified deliverables, completed and verified for correctness by the quality control process.

The project management plan, which contains the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.

The responsibility assignment matrix, which describes the responsibilities for correcting the scope in case the client rejects the project deliverables.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Nancy is the Project Manager of an overpass project. The project is 18% complete. The Steering Committee will meet tomorrow. She is looking at the schedule forecasts for all of the following except: Select one:

to find out how much more the project will cost.

to identify any necessary change requests.

to determine if the project is within the defined schedule tolerance ranges.

to find out how much the schedule is delayed.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The expected cost necessary to complete the remaining work for a schedule activity, work breakdown structure component, or the project. This is the description of which of the following terms:

Schedule Performance

Cost Performance Index

c. Estimate to Complete

Estimate at Completion

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The final performance report of a project that was completed 6 months late shows the Cost Performance Index (CPI) as 0.83. What is the Schedule Performance Index (SPI) of this project?

SPI = 1.00

SPI = 0.83

SPI = 0.50

Cannot be determined with the given information

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The results of the Risk Response Planning process include:

Secondary risks, process updates, and risk owners

Contingency plans, project management plan updates, and sensitivity analysis

Risk triggers, contracts, and a risk list

Residual risks, contingency plans, and contingency reserves

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the best method to control changes in the project? Select one:

Make changes quickly when they occur

Direct changes to the change control board (CCB)

Prevent changes from being made

Look for sources of changes

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Similar Resources on Wayground