PMI-SP Practice Exam  Quiz 3

PMI-SP Practice Exam Quiz 3

Assessment

Quiz

others

Easy

Created by

Meshaal Alabdulaziz

Used 2+ times

FREE Resource

Student preview

quiz-placeholder

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Archive the project records.
Summarize the project risks costs.
Summarize the project variance.
Close the project office.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

Diane
Project sponsor
Risk owner
Subject matter expert

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to one you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following, except for which one?

Identify typical schedule milestones.
Create parametric estimates for repetitive activities.
Save time creating activity duration estimates.
Import activity attributes.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You work as a project manager for BlueWell, Inc. You are in the process of identifying all the people and organizations impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

Expert judgment
Project charter
Stakeholder analysis
Stakeholder register

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

Project calendar
Activity attributes
Resource calendar
Schedule management plan

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

Stakeholder classification
Project management team's classification
Assessment information
Identification information

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be considered successful?

The project meets or exceeds the expectations of the stakeholders
The building is complete and handed over to the authority concerned.
The keys of the first flat are handed over to the owner of the flat.
Successful possession of all flats is made.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?