1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is struggling to set clear objectives for a new software development project. The team is unsure about the project's direction. What should the project manager focus on first?
Developing a detailed project schedule
Creating S.M.A.R.T objectives aligned with the project aim
Assigning tasks to team members
Conducting a risk assessment
Answer explanation
The project manager should first create S.M.A.R.T objectives aligned with the project aim. This provides clear direction and measurable goals, ensuring the team understands the project's purpose before moving on to scheduling or task assignments.
2.
FILL IN THE BLANK QUESTION
2 mins • 4 pts
The construction project team realizes they've built an exact replica of the Taj Mahal instead of the planned shopping mall. The stakeholders, a mix of bewildered local politicians and eccentric businessmen reminiscent of Jagathy Sreekumar and Innocent, stand slack-jawed at the site. As chaos ensues, with workers running around like a Priyadarshan climax scene, it becomes clear that in the planning phase, they overlooked the critical step of actually defining the project scope and _.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A software development team is consistently delivering features that don't meet user expectations, despite following the project plan. What aspect of project management needs immediate attention?
Stakeholder communication
Resource allocation
Quality assurance processes
Risk management
Answer explanation
The team is delivering features that don't meet user expectations, indicating a failure in quality assurance processes. Improving these processes will help ensure that the features align with user needs and expectations.
4.
FILL IN THE BLANK QUESTION
2 mins • 4 pts
The project to modernize Thrissur Pooram hits a snag when the team, led by contractor Kottayam Kunjachan, discovers the new high-tech elephant costumes are allergic to fireworks. As news spreads, causing more drama than a Mammootty-Suresh Gopi face-off, chaos erupts faster than a Dileep comedy sequence. Local politicians argue like a heated Asianet News debate, while traditionalists protest louder than percussion at Tripunithura temple. Amidst the mayhem, our hero realizes that a comprehensive _ identification and planning could have prevented this jumbo-sized fiasco.
5.
FILL IN THE BLANK QUESTION
3 mins • 5 pts
At Malabar Tech, project manager Ravi feels like he's trapped in "Manichitrathazhu." What started as a smooth project is now spiraling into resistance. The stakeholders, once supportive like Ganga in her calm moments, have now turned into Nagavalli, pushing back on every decision. Ravi knows if this continues, the project could end up like an unsolved mystery. What strategy should Ravi adopt to manage the growing resistance and win back the stakeholders' support before his project becomes a full-fledged nightmare? Ans: Develop a tailored _(1) plan for different _(2) groups
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is consistently falling behind schedule due to unexpected resource shortages.
What tool could have helped prevent this issue?
Gantt Chart
Work Breakdown Structure
SWOT Analysis
Stakeholder Register
Answer explanation
A Gantt Chart visually represents project timelines and resource allocation. By using it, the project manager could have identified potential resource shortages early, allowing for adjustments to the schedule or resource planning.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager needs to gather detailed insights about user experiences with a new product.
Which research method would be most appropriate?
Quantitative surveys
Secondary research
In-depth interviews
Observation of public behavior
Answer explanation
In-depth interviews are ideal for gathering detailed insights about user experiences, allowing for open-ended questions and deeper understanding, unlike quantitative surveys or secondary research which provide less depth.
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Gantt Charts and MS Project

Quiz
•
12th Grade
16 questions
Vocab Quiz Week 5 (Market Research)

Quiz
•
9th - 12th Grade
20 questions
1.01 Study Guide

Quiz
•
9th - 12th Grade
17 questions
24-25 PM1 Charter Creation & Decision Making

Quiz
•
9th - 12th Grade
17 questions
Graphic Design Basics

Quiz
•
9th - 12th Grade
20 questions
Revision marketing (business) A level

Quiz
•
12th Grade
18 questions
Quality Management Quiz (ITPM)

Quiz
•
12th Grade
16 questions
Market Research

Quiz
•
12th Grade
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade