t-level Construction Project Documentation Quiz

t-level Construction Project Documentation Quiz

12th Grade

15 Qs

quiz-placeholder

Similar activities

8710_350_uko2_ppt_2 T-Level Building Materials and Design Quiz

8710_350_uko2_ppt_2 T-Level Building Materials and Design Quiz

12th Grade

15 Qs

Data & information Quiz

Data & information Quiz

12th Grade

20 Qs

UNIT 104 lesson 3

UNIT 104 lesson 3

12th Grade

15 Qs

5357-105 #02B Technical and functional information

5357-105 #02B Technical and functional information

12th Grade

10 Qs

G11_EIM Q2_Quiz

G11_EIM Q2_Quiz

12th Grade

20 Qs

Architectural Drawing Concepts Quiz

Architectural Drawing Concepts Quiz

9th - 12th Grade

11 Qs

Health and Safety in Building Services Engineering

Health and Safety in Building Services Engineering

12th Grade

20 Qs

AC1.6 Communication Pipe Quiz

AC1.6 Communication Pipe Quiz

12th Grade

15 Qs

t-level Construction Project Documentation Quiz

t-level Construction Project Documentation Quiz

Assessment

Quiz

Construction

12th Grade

Medium

Created by

Trevor Armstrong

Used 5+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a formal agreement between a contractor and the client for a construction project based on the information provided?

Take-off sheet

Contract

Schedule of rates

Estimate

Answer explanation

A formal agreement between a contractor and the client for a construction project is called a 'Contract'. It outlines the terms, responsibilities, and scope of work, ensuring both parties are aligned on expectations.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document accompanies a shipment from a supplier and describes the goods and quantities being delivered?

Quotation

Delivery note

Purchase order

Wiring diagram

Answer explanation

The delivery note is the document that accompanies a shipment, detailing the goods and their quantities. It serves as proof of delivery and helps the recipient verify the items received against the order.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is a fixed price for goods and services offered by contractors or subcontractors to potential clients?

Quotation

Schedule of rates

Take-off sheet

Wiring diagram

Answer explanation

A quotation is a document that provides a fixed price for goods and services from contractors or subcontractors to potential clients, making it the correct choice for this question.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is a technical drawing provided by the client to building services engineers for the installation of electrical systems?

Wiring diagram

Delivery note

Schedule of rates

Quotation

Answer explanation

A wiring diagram is a technical drawing that provides detailed information on the installation of electrical systems, making it essential for building services engineers. The other options do not serve this purpose.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is an agreed schedule of costs for building materials for a set period between contractors and suppliers?

Schedule of rates

Estimate

Contract

Take-off sheet

Answer explanation

A schedule of rates is a pre-agreed list of costs for building materials, allowing contractors and suppliers to reference prices for a specific period. This makes it the correct choice for the question.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is a prediction of costs for building work provided by contractors to clients?

Estimate

Bill of quantities

Purchase order

Wiring diagram

Answer explanation

An estimate is a document that provides a prediction of costs for building work, helping clients understand potential expenses before the project begins. Other options like bill of quantities and purchase orders serve different purposes.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is used by estimators to calculate quantities of building materials and labor costs from working drawings and specifications?

Take-off sheet

Contract

Quotation

Delivery note

Answer explanation

A take-off sheet is used by estimators to quantify building materials and labor costs based on working drawings and specifications, making it the correct choice for this purpose.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?