Parte 4 API 570

Parte 4 API 570

University

28 Qs

quiz-placeholder

Similar activities

OM SAMPLE QUIZ

OM SAMPLE QUIZ

University

25 Qs

Special Probability Distribution

Special Probability Distribution

University - Professional Development

30 Qs

Sem 2 Unit 3

Sem 2 Unit 3

9th Grade - Professional Development

29 Qs

Normal Distributions Unit Review

Normal Distributions Unit Review

11th Grade - University

30 Qs

Microeconomics Practice Test

Microeconomics Practice Test

12th Grade - University

24 Qs

Absolute Value Review

Absolute Value Review

9th Grade - University

23 Qs

Heat Treatment in Metals Quiz

Heat Treatment in Metals Quiz

University

33 Qs

Boy Scout Questions

Boy Scout Questions

KG - Professional Development

24 Qs

Parte 4 API 570

Parte 4 API 570

Assessment

Quiz

Mathematics

University

Hard

Created by

Ely Ramirez

Used 4+ times

FREE Resource

28 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1. Who shall exercise control of the piping system inspection program?
A) Authorized Inspection Agency
B) Owner/User Engineering Organization
C) Owner/User's Inspection Organization
D) Owner/User Maint/Operating Organization

Answer explanation

Correct answer: API 570 4.1: The Owner/User’s Inspection Organization is responsible for the control of inspection activities.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2. Who shall control activities relating to rating/repair/alteration of its piping systems?
A) Owner/User Engineering
B) Authorized Inspection Agency
C) Owner/User’s Inspection Organization
D) Owner/User Maint/Operating Organization

Answer explanation

Correct answer: API 570 4.1: The Owner/User Engineering Organization is responsible for rating, repairs, and alterations.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

3. Which of the following should be established for process parameters?
A) Integrity Operating Envelopes
B) Standard Operating Procedures (SOPs)
C) Safety Operating Envelopes
D) Process Safety Limits (PSLs)

Answer explanation

Correct answer: API 570 4.3.1.4: Integrity Operating Envelopes (IOWs) should be established for process parameters.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

4. Process parameters that could impact equipment integrity include all except:
A) Temperatures and pressures
B) Fluid velocities and flow rates
C) Cleaning procedures during shutdown
D) Levels of corrosive constituents, chemical compositions and pH

Answer explanation

Correct answer: API 570 4.3.1.4: Cleaning procedures during shutdown are not typically part of Integrity Operating Envelopes.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. Particular attention to monitoring integrity operating envelopes should also be provided during:
A) Start-ups
B) Shutdowns
C) Normal operations
D) Significant process upsets

Answer explanation

Correct answer: API 570 4.3.1.4: Start-ups require special attention to monitor integrity operating envelopes.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. Authorized piping inspectors shall have education and experience in accordance with:
A) Annex A of API 570
B) Owner/User’s Quality Manual
C) API Inspector Certification Program
D) None of these are correct

Answer explanation

Correct answer: API 570 4.2: Authorized inspectors must have education and experience as per Annex A.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. Whenever the term inspector is used in API 570, it refers to:
A) Examiner
B) QA or QC Inspector
C) AWS Certified Welding Inspector
D) Authorized Piping Inspector

Answer explanation

Correct answer: API 570 4.2: “Inspector” refers to the Authorized Piping Inspector.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?