Critical Path Analysis and Algorithms

Critical Path Analysis and Algorithms

Assessment

Interactive Video

Mathematics, Computers, Business, Education, Instructional Technology

9th - 12th Grade

Practice Problem

Hard

Created by

Liam Anderson

FREE Resource

This video tutorial introduces the critical path algorithm, focusing on version one. It explains the steps to create a priority list by identifying critical paths in a task diagram. Through an example, the video demonstrates the trial-and-error process of finding the longest path and updating the priority list. The tutorial concludes with a brief introduction to version two, which uses the backflow algorithm to simplify the process.

Read more

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of the Critical Path Algorithm?

To create a priority list based on task importance

To find the shortest path in a network

To allocate resources efficiently

To determine the minimum completion time for a schedule

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which step involves removing a task from the diagraph in Version One of the Critical Path Algorithm?

Step 3

Step 4

Step 2

Step 1

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the example, what is the total time for the critical path starting at Task 1 and going through Task 4 and Task 7?

15 hours

19 hours

17 hours

23 hours

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the total time for the path from Task 2 to Task 5 to Task 8?

17 hours

19 hours

23 hours

15 hours

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which task is added to the priority list after Task 1 is eliminated?

Task 4

Task 5

Task 3

Task 2

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the total time for the critical path starting at Task 6 and going to Task 8?

7 hours

14 hours

12 hours

9 hours

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which tasks are added to the priority list when there are two critical paths starting at different vertices?

Task 6 and Task 7

Task 4 and Task 5

Task 2 and Task 3

Task 8 and Task 9

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?