GMJ 6189-33 unit 301

GMJ 6189-33 unit 301

Vocational training

20 Qs

quiz-placeholder

Similar activities

Workplace Safety Quiz

Workplace Safety Quiz

Professional Development

25 Qs

Communication within the building services

Communication within the building services

KG - University

15 Qs

HSE Class Test (Resit) SAQ

HSE Class Test (Resit) SAQ

KG - University

24 Qs

Construction Quiz End of Unit

Construction Quiz End of Unit

12th Grade

20 Qs

Health and Safety Laws

Health and Safety Laws

11th Grade

16 Qs

HSE Lecture 3 - GMT07

HSE Lecture 3 - GMT07

12th Grade

23 Qs

Understanding Earthing Arrangements

Understanding Earthing Arrangements

12th Grade - University

20 Qs

Safety for Electricians (Electrical L1) Quiz

Safety for Electricians (Electrical L1) Quiz

12th Grade

18 Qs

GMJ 6189-33 unit 301

GMJ 6189-33 unit 301

Assessment

Quiz

Construction

Vocational training

Easy

Created by

Glen Johnson

Used 1+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following calculates how much a project will cost?

Clerk of Works.

Estimator.

Quantity Surveyor.

Architect.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Quantity Surveyor is responsible for producing the

architectural drawings

bill of quantities

work programme

variation order

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a customer asks the plumber to make changes to an installation, which of the following is it most important to confirm in writing?

Details of the initial request.

The materials needed for the work.

The estimated delivery date.

The agreed time and cost for the work.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following documents is a request for payment?

Invoice.

Bill of quantities.

Quotation.

Estimate.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As an apprentice, which of the following are you allowed to do?

Work without supervision.

Supervise others.

Work only with supervision.

Work with minimal supervision.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As an apprentice, you are installing gas pipework and you notice that the route the pipework is going to take will cause problems later. You should inform

the contract manager

the architect

your immediate supervisor

the clerk of works

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a customer asks the plumber to make changes to an installation, which one of the following documents must be issued by the architect to ensure payment for the additional work and materials?

Quotation.

Estimate.

Variation order.

Delivery note.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?