Project/Maintenance Management Q2
Authored by Rene Pacturan
Construction
University
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
20 sec • 2 pts
What is the SLACK for this activity B?
7
3
1
2.
MULTIPLE CHOICE QUESTION
20 sec • 2 pts
What is the FLOAT of an ACTIVITY in CRITICAL PATH?
2
1
0
3.
MULTIPLE CHOICE QUESTION
45 sec • 2 pts
Which of the following is/are TRUE for a CRITICAL Path?
(i) Is the LONGEST PATH of the network
(ii) Is the EARLIEST COMPLETION DATE of the project
(iii) Is the path where all activities have ZERO FLOAT
i and ii
i and ii
i, ii, and iii
4.
MULTIPLE CHOICE QUESTION
45 sec • 2 pts
What is the CRITICAL PATH of this project?
1-2-3-4-5-6
1-2-4-5-6
1-2-3-5-6
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The team monitors resources, costs, quality, and budgets. It also revises or changes plans and shifts resources to meet time and cost demands
PLANNING
SCHEDULING
CONTROLLING
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?