Project/Maintenance Management Q2

Authored by Rene Pacturan

Construction

University

Used 2+ times

Project/Maintenance Management Q2
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 2 pts

Media Image

What is the SLACK for this activity B?

7

3

1

2.

MULTIPLE CHOICE QUESTION

20 sec • 2 pts

What is the FLOAT of an ACTIVITY in CRITICAL PATH?

2

1

0

3.

MULTIPLE CHOICE QUESTION

45 sec • 2 pts

Which of the following is/are TRUE for a CRITICAL Path?

(i) Is the LONGEST PATH of the network

(ii) Is the EARLIEST COMPLETION DATE of the project

(iii) Is the path where all activities have ZERO FLOAT

i and ii

i and ii

i, ii, and iii

4.

MULTIPLE CHOICE QUESTION

45 sec • 2 pts

Media Image

What is the CRITICAL PATH of this project?

1-2-3-4-5-6

1-2-4-5-6

1-2-3-5-6

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

The team monitors resources, costs, quality, and budgets. It also revises or changes plans and shifts resources to meet time and cost demands


PLANNING

SCHEDULING

CONTROLLING

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?