1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. What is the duration of PPP’s New PPA?

1 year

2 years

1 year with an option to extend for further extension subject to EC’s decision

2 years with an option to extend for further extension subject to EC’s decision

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. Which of the outages below are described in the PPA?

Reserved, Maintenance, Scheduled & Forced Outages

Scheduled, Maintenance, Emergency & Reserved Outages

Scheduled, Maintenance, Major Overhaul & Forced Outages

Scheduled, Emergency, Major Overhaul & Forced Outages

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Test(s) requested by Plant is considered as Forced Outage, except test during.

i.                 TAAC Test

ii.                Monitoring Test

iii.               Startup on Test Energy

iv.               Revalidation Test (during non-Scheduled Outage period)

i and ii

i, ii and iii

iii and iv

all of the above

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. What is contained in the Annual Scheduled Available Capacity (ASAC)?

The schedule of hourly Availability in MW for every hour of each day of a Contract Year

The schedule of hourly Availability in MWh for every hour of each day of a Contract Year

The schedule of hourly Unavailability in MW for every hour of each day of a Contract Year

The schedule of hourly Availability in MW for every day of each month of a Contract Year

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. 4% of UOL1 is equivalent to how many days FO (i.e.350MW loss)?

10 days

15 days

20 days

25 days

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. Test Energy Payment (TEP) consists of Fuel Payment and no VOR Payment:

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

There is an Unutilised Scheduled Outage Hours (USOH) reimbursement under the New PPA:

True

False

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?