Project Management Quiz Mid

Quiz
•
Other
•
Professional Development
•
Medium
Marjan Farshadi
Used 3+ times
FREE Resource
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The PMBoK describes a project as a permanent effort aimed at producing a unique product or service.
True
False
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Mia is planning a school project and needs to estimate how long each task will take. In project management, estimating activity durations involves guessing how long the project will take.
True
False
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
James is working on a project and needs to consider the interests of external stakeholders. Do external stakeholders refer to people within the organization who have an interest in the project's outcome?
True
False
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a software development project using Agile methodology, a challenge faced by Liam's team is:
A flexible leader could elevate the project.
The self-organizing team lacks a clear manager, and the customer may take the lead.
A strict leader is present to ensure timelines are met.
The team has a designated manager.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Estimating duration in project management is considered a qualitative assessment.
True
False
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The microsystem approach focuses on highlighting large, hard-to-duplicate systems.
True
False
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the PDSA Cycle, steps for developing and testing a strategy include:
Select measures to track progress, assess results against criteria, conduct small change trials, tailor changes to the organization, and manage obstacles.
Select measures to track progress, develop changes, explore possible interventions, tailor changes to the organization, and manage obstacles.
Plan for the change, develop changes, conduct small change trials, tailor changes to the organization, and manage obstacles.
Select measures to track progress, develop changes, conduct small change trials, tailor changes to the organization, and manage obstacles.
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project sponsor is someone who simply follows instructions throughout the project management process.
True
False
Similar Resources on Wayground
9 questions
Project Execution Methodology: Preliminary Contract Activity

Quiz
•
Professional Development
10 questions
VMV Launch - Fun Quizz

Quiz
•
Professional Development
10 questions
PMP Test Questions

Quiz
•
Professional Development
10 questions
Quiz - 4th RTC Indonesia Conference

Quiz
•
Professional Development
10 questions
ITIL Know the purpose 15 ITIL practices

Quiz
•
Professional Development
10 questions
Knowledge and Innovation Quiz

Quiz
•
Professional Development
10 questions
Strategic Thinking for Professional

Quiz
•
Professional Development
10 questions
How much do you know about SCORE?

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade