PMP Exam Crash Program 2024

Quiz
•
Professional Development
•
Professional Development
•
Hard
Training eNetwoQ ServIT Indonesia
Used 1+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The development team completed 24 of the planned 28 story points for the sprint. During the sprint review, the customer approves the completed deliverables, but he admonishes the team as being lazy and incompetent for failing to complete the entire sprint backlog. How should the scrum master respond?
Meet with the customer in private and challenge them to be more respectful to the team
Discuss the reasons for the failed sprint during the next daily standup meeting
Encourage the team to commit to completing fewer story points for the next sprint
Challenge the team to work on their days off until they cover the shortfall
Answer explanation
The correct response is to meet with the customer privately to address their disrespectful comments. This protects the team's morale and fosters a constructive relationship, rather than publicly discussing failures or pushing for unrealistic commitments.
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are acquiring the necessary resources for your project. The organization where you are employed is an international company with locations in several countries. With personnel located around the globe, you will be forming your project team as a virtual team, and the team members will be allowed to work from their home offices. What special considerations do you need to take into account while working with your team?
Project expenses
Communication planning
Pre-assigned team members
Team members with disabilities or mobility issues
Answer explanation
Effective communication planning is crucial for virtual teams, as team members are dispersed globally. It ensures clarity, coordination, and engagement, addressing potential challenges like time zone differences and varying communication styles.
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The quality management has been perfect for the project up to this point. Suddenly, the quality assurance (QA) lead who developed and performed most of the quality activities for the project has been temporarily reassigned to help another project. What should the project manager do?
Submit a change request to adjust the cost baseline and the schedule baseline
Request the team to develop replacement quality activities
Assign another team member to carry out the originally planned quality activities
Pause quality activities until the QA lead returns to the project
Answer explanation
Assigning another team member to carry out the originally planned quality activities ensures continuity in quality management, preventing delays and maintaining project standards while the QA lead is temporarily unavailable.
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are preparing for an upcoming software development project. The project will be initiated and planned using a predictive approach, while the development team will use Kanban. A budget has been established for training, and you need to determine how to allocate those funds. What is your best course of action?
Send the development team to a seminar on maximizing WIP
Provide training to transform T-shaped people into I-shaped people
Deliver training to convert I-shaped people into T-shaped people
Train the team on how to best prioritize the features to be developed
Answer explanation
Delivering training to convert I-shaped people into T-shaped people enhances team versatility, enabling them to collaborate better and adapt to various tasks in a Kanban environment, which is crucial for effective project execution.
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are planning a kick-off meeting for your new project. The meeting will communicate the start of the project, key milestones, and other relevant information. Which of the following best describes the objective of this meeting?
Inform and engage stakeholders and gain commitment
Manage threats and opportunities throughout the project
Ensure that the project is completed on schedule and budget
Secure resources required to complete project deliverables
Answer explanation
The objective of the kick-off meeting is to inform and engage stakeholders about the project, ensuring they understand key milestones and fostering commitment to the project's success.
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are a project manager conducting a meeting with your project team. The goal of the meeting is to improve the overall team environment to enhance project performance. The meeting becomes contentious with team members interrupting each other and being disrespectful to each other's suggestions. You attempt to return civility to the meeting by establishing ground rules for acceptable behavior, but working relationships may already be damaged. What might you have missed that could have prevented this situation?
Sharing the team management plan with the project team
Involving the project team in the creation of a team charter and gaining agreement with the content
Allowing the team members to work independently and avoid interaction
Making sure each team member has a copy of the project charter
Answer explanation
Involving the project team in creating a team charter fosters collaboration and respect, establishing a foundation for positive interactions. This could have prevented the contentious atmosphere by aligning team values and expectations.
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A vendor has been contracted by a buyer to develop a new device. The vendor insisted that the contract thoroughly capture the device specifications. The buyer does not have clear requirements upfront and, therefore, requested that the vendor develop the device using agile. The vendor delivers as per the contract, but the buyer is not satisfied with the outcome. Which Agile Manifesto's value was most likely not appropriately applied?
Business people and developers must work together
Individuals and interactions over processes and tools
Pair programming over continuous integration
Customer collaboration over contract negotiations
Answer explanation
The vendor's focus on contract specifications over ongoing customer feedback indicates a failure to apply 'Customer collaboration over contract negotiations'. Agile emphasizes adapting to customer needs rather than strictly adhering to contracts.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Quiz Lesson 3 - Topic G (Quality)

Quiz
•
Professional Development
10 questions
PMP - Roles & Organizations

Quiz
•
Professional Development
15 questions
All-In-One Project+ PK0-005 Exam Guide - Chapter 09

Quiz
•
Professional Development
10 questions
Project Management Module

Quiz
•
Professional Development
10 questions
Soft Skills in the work place

Quiz
•
Professional Development
10 questions
JCI Pre-Assessment

Quiz
•
Professional Development
10 questions
Which Leadership Style will you adopt

Quiz
•
Professional Development
14 questions
RDL1-Test Planning

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade