28 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance team is requesting a project budget for the new product. What should the team do to address this request?

Work with the finance team to transition to incremental budgeting.

Request the finance team to allocate a budget based on historical data.

Provide the budget to the finance team for only the planned increments.

Extrapolate the budget based on the current cost performance index (CPI).

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project. Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work out a permanent solution to the issues, but this is also unsuccessful. What should the project manager do next?

Escalate the issue to a higher authority.

Suspend the two key team members immediately.

Put the issue on the agenda for the next team meeting.

Reassign one of the key team members to a different task.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before. How should the agile project leader resolve this situation?

Update the restriction log with the new team capacity.

Explain the new project requirements to the team.

Update the project budget with the released team members.

Explain the new team velocity to the customer.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates. What should the project manager do to ensure timely delivery?

Ask the team leader to assign other resources.

Update the issue log.

Include this in the risk register.

Escalate the issue to the functional manager.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase. While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

Create a product backlog

Perform sprint reviews with the team

Assess the previous project velocity

Reduce the story size by splitting stories

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?

Cost oriented

Deliverable oriented

Customer oriented

Team oriented

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance. What immediate action should the project manager take to improve the situation?

Communicate this issue to the human resources department.

Provide additional training to the new hire.

Increase team cohesiveness by sharing information and experiences openly.

Update the issue log and define the mitigation strategy.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?