30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A software development company is tasked with creating an e-commerce platform. During project planning, they define all the tasks, deadlines, and resources required to complete the project. Which of the following best describes this process?
Project Charter
Project Plan
Risk Assessment
Requirements Documentation
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A team is developing a new inventory management system. The system must be delivered in six months, and the client has specified clear deadlines for each milestone. The project manager creates a timeline of tasks to ensure the system is delivered on time. What is this process called?
Scheduling
Quality Assurance
Testing
Deployment
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An IT company is planning a project to integrate their accounting software with a customer relationship management system (CRM). During planning, they discuss potential technical issues and how they will handle them if they arise. What activity are they performing?
Resource Allocation
Risk Management
Configuration Management
Product Evaluation
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company is building a web-based application where customers can create profiles, browse products, and place orders. Each of these features is developed and tested independently before being combined. Which stage of project management does this describe?
Requirements Analysis
System Integration
Software Testing
Deployment
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A software team is assigned the task of creating an online booking system for a travel agency. After gathering initial requirements from the client, they outline the features and limitations of the system in a document. What is this document called?
Functional Requirements Document
User Guide
Test Plan
Product Roadmap
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a large-scale software project, a company needs to ensure that the software system supports multiple users performing different tasks simultaneously, such as managing products, handling orders, and maintaining customer data. Which of the following best describes this scenario?
System Design
Functional Requirement
Non-functional Requirement
Risk Mitigation
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A software engineering firm is building a mobile application. They focus on ensuring that the app is user-friendly, loads quickly, and operates smoothly without crashing. Which type of requirements are they focusing on?
Functional Requirements
Non-functional Requirements
Business Requirements
Technical Requirements
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?