1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

While under development the environment in which a product will be used changed. What is the effect on the product backlog?

It is archived and a new Product Backlog is created to take its place.

There is no effect, because it has to stay the same until the end of the project.

It evolves to reflect what the product needs to be most valuable

It is converted into a requirements specification to ensure stability

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

All work to be done by Development Team must ultimately originate from Product Backlog?

True

False

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is required by Scrum ?

Sprint restrospective.

Members must stand up at the Daily Scrum.

Sprint Burndown Chart.

Release Planning.

All options are correct.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the word 'development' mean in the context of Scrum? Select the best option.

Development of an operational environment for the Product.

Product development, its releasing and sustaining.

Software and hardware development.

Research and identifying of viable markets, technologies, and Product capabilities.

Complex work that can include all the suggested options and even more

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The time-box for the Sprint Planning meeting is?

4 hours.

8 hours for a monthly Sprint. For shorter Sprints it is usually shorter.

Whenever it is done.

Monthly.

6.

MULTIPLE SELECT QUESTION

1 min • 1 pt

How does the Scrum Master help the Product Owner? Select the three most appropriate answers.

Understanding product planning in an empirical environment.

Facilitating Scrum events as requested or needed.

Introducing cutting edge development practices.

Finding techniques for effective Product Backlog management.

Leading and coaching the organization in its Scrum adoption.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the role of Management in Scrum?

Continually monitor staffing levels of the Development Team.

Monitor the Development Team's productivity.

Support the Product Owner with insights and information into high value product and system capabilities. Support the Scrum Master to cause organizational change that fosters empiricism, self-organization, bottom-up intelligence, and intelligent release of software.

Identify and remove people that aren't working hard enough.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?